RESOLVED that (1) the Planning Performance Agreement for the proposed Surbiton Hospital Redevelopment be noted and also it be noted that there was a view that the mix of development for the site set out in paragraph 9 of the report should not be pre-determined. (2) regular progress reports be submitted as a matter of course for Surbiton Neighbourhood Committee and South of the Borough Neighbourhood Committee. Reason for the decision To keep Members informed about the Planning Performance Agreement and the proposed timetable and milestones up to submission of the planning application.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
In November, members of the local neighbourhood committees and Development Control Committee received an information item entitled ‘Planning Performance Agreement Charter’ (PPA) which set out the purpose and role of such agreements in major developments. The redevelopment of the Surbiton Hospital site is a pilot for the use of PPA's in Kingston and monitoring its use will inform a PPA Charter. The charter will state the local authority’s intentions in entering into Planning Performance Agreements with developers. This report therefore updates members on the Planning Performance Agreement in place for the Surbiton Hospital redevelopment, how it has developed and is to be used in setting milestones and defining the parameters, including consultation with members and community engagement. The PPA will be the vehicle within which a planning application can be submitted.
Recommendation
It is RECOMMENDED that the Planning Performance Agreement for the proposed Surbiton Hospital Redevelopment be noted.
Reason for recommendation
To inform the Committee of the Planning Performance Agreement and the proposed timetable and milestones up to submission of the planning application.
Background
1. Planning Performance Agreements (PPAs) were introduced by the Department for Communities and Local Government (DCLG) in 2006 as a new way to manage large scale planning applications. Members were previously informed of officers’ intentions to pilot the use of the PPA process in the proposed redevelopment of the Surbiton Hospital site.
2. The proposed Surbiton Hospital Redevelopment is a significant proposal in which the Primary Care Trust and RBK (Learning and Children’s Service) have agreed to enter into a partnership to redevelop the site for a new polyclinic and 2 form entry primary school.
3. Since August 2009, preliminary discussion have taken place between the parties to establish the most appropriate way forward and the nature of the partnership agreement. B2
4. In November, Consultants Lynda Addison & Associates were commissioned to assist the Council in developing the PPA. An inception meeting was held in December, followed by workshops in late December and January, to establish the project vision, develop objectives, and establish key issues and tasks. A first priority was to set the key milestones to focus the submission of pre application material for consideration including Member involvement and public engagement.
5. The Primary Care Trust proposals for the demolition of the existing Surbiton Hospital and the redevelopment to provide a polyclinic require the approval of a Full Business Case to the Strategic Health Authority. Prior steps include the submission of an Outline Business Case and the support of the Primary Care Trust Board. On 5 February the PCT Board expressed their support for the Planning Performance Agreement and the milestones set out. Officers are currently in the process of working to the timetable to ensure the milestones are met.
PRINCIPLES OF THE PLANNING PERFORMANCE AGREEMENT
6. The Planning Performance Agreement (PPA) has been agreed as the appropriate Project Management Framework between the PCT, Children and Learning Services (as applicant) and the Council for managing the Surbiton Hospital planning process. It sets out the agreed vision and objectives for the site, the key issues which will need to be addressed, details of the programme and the key tasks required to take the proposals through the pre application and planning process.
7. The benefits of the PPA have been identified as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.