Resolved
RESOLVED that the revised 2011/12 LIP Programme be endorsed for approval by the Executive. REASON FOR DECISION To provide the Executive with Neighbourhood views.
Surbiton Neighbourhood Committee approved this item on Wednesday 2 February 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the revised 2011/12 LIP Programme be endorsed for approval by the Executive. REASON FOR DECISION To provide the Executive with Neighbourhood views.
Transport for London announced that that the Government’s Comprehensive Spending Review would have an implication on the previously announced LIP funding for 2011/12. The implication for RBK is that a cut of 4% needs to be found in the 2011/12 financial year against the programme already endorsed by Executive.
Possible options for making the savings were discussed when the Draft Second Local Implementation Plan (LIP2) item was considered at the Executive meeting on 30 November 2010.
It is RECOMMENDED that the revised 2011/12 LIP Programme be endorsed and any Member comments on the proposals be provided to the Executive.
To provide the Executive with Neighbourhood views.
1. In early 2010, Transport for London (TfL) wrote to RBK to advise on the indicative LIP settlement for the 2011-12 financial year. The Council subsequently prepared a list of transport initiatives (Annual Spending Submission) which complied with TfL’s LIP guidance framework. These initiatives were endorsed by the Neighbourhood Committees in July 2010 and the Executive on 7 September 2010. This LIP Annual Spending Submission was submitted to TfL on 8 October 2010.
2. Later in October the new Coalition Government reported on the findings of its Comprehensive Spending Review (CSR On 4 November 2010 TfL wrote to RBK with information on how the CSR had affected RBK’s LIP funding allocations for 2011/12 (and also for 2012/13 and 2013-14).
3. As part of the Draft Second LIP item, the Executive was asked at its 30 November 2010 meeting to provisionally consider where the savings could be made for 2011/12. A summary of the noted changes is at Annex 1.
4. On 16 December 2010, TfL wrote again to RBK to confirm that the Annual Spending Submission made in October was acceptable; however it would be up to RBK to identify and confirm where the savings for 2011/12 would be made. C2
5. This report sets out what the revised 2011/12 LIP budgets are and how this affects the programme previously endorsed by the Executive on 7 September 2010 (and Neighbourhoods in the July 2010 cycle). It also considers the savings discussed at the 30 November 2010 meeting of the Executive.
6. In any case, the LIP funding received from TfL will support a range of local transport improvements including the Tolworth Broadway Major scheme, a number of Strategic Corridor improvements (such as New Malden High Street, the Surbiton project, the A2043 & Burlington, St James’s Road), Cycling schemes (including Biking Borough, Greenways and cycle parking schemes), bus stop accessibility, various neighbourhood engineering schemes which address local safety and accessibility, Smarter Travel initiatives and Principal Road maintenance.
7. The 2011/12 Programme also represents year 1 of RBK’s new LIP2 Programme of Investment.
ANALYSIS OF LIP SETTLEMENT AND PROPOSAL
8. This Committee is requested to acknowledge and endorse the finalised LIP funding allocations made by TfL, and to bear in mind the potential options for making savings discussed at the 30 November 2010 meeting of the Executive. This will ensure that officers can commence preparation of scheme development and implementation of the 2011/12 Programmes before 1 April 2011 to ensure full financial spend in 2011/12.
9. The implications for RBK of the LIP funding cuts are shown in Table 1 and these only affect the Corridors, Neighbourhoods and Supporting Measures Programme.
Table 1: Savings Required for Corridors, Neighbourhoods and Supporting Measures Programme during LIP2 (2011-14) 2011-12 2012-13 2013-14 (Confirmed) (Indicative) (Indicative) Previous Allocation £1,680k £1,683k £1,683 Revised Allocation £1,610k £1,544k £1,324 Saving Required -£70k -£139k -£359k % -3.9% -7.8% -20.1%
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 77 KB | Download |
PDF |
LIP Funding 2011/12Report | 164 KB | DownloadRead as text |
Follow Surbiton Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Community Grants ProgrammeRESOLVED that: ( i ) the application for a £2,800 Neighbourhood Community Grant from Surbiton Town Centre Partnership... | Approved | Open |
| 9 Jun 2026 | Appointment of Chair and Vice-ChairRESOLVED that: 1. Councillor Tom Reeve be appointed Chair of the Committee for the Municipal Year 2026/27 until the f... | Decided | Open |
| 9 Jun 2026 | Double Yellow Lines on Villiers Avenue - Objections to Traffic Management OrderRESOLVED that: 1. the comments and objections received on the Traffic Management Order (TMO) on conversion of Single ... | Noted | Open |
| 9 Jun 2026 | Planning ApplicationsRESOLVED to PERMIT subject to the conditions set out in the report including such amendments, additions and/or deleti... | Decided | Open |
| 9 Jun 2026 | Councillor Ward Funding Arrangements 2026/27RESOLVED that the Committee’s current working arrangements for the allocation of Councillor Ward Funding, as set out ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.