RESOLVED that : 1. the South London Waste Plan, incorporating the Inspector’s endorsements, is adopted. 2. authority is delegated to the Interim Head of Planning and Transport to make minor formatting corrections to the adopted document, if required, and to attend to the statutory requirements of adoption. Reasons for the decision To provide clear guidance on the number of waste facilities which need to be developed to meet the boroughs’ waste management targets. To ensure that waste facilities are developed in appropriate locations across the four boroughs to high standards of design. To ensure that the four boroughs do not incur an EU fine for not having a waste plan in place.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Report to the Councils of the London Boroughs of Croydon, Kingston-upon- Thames, Merton & Sutton by Brian Cook BA(Hons) DipTP MRTPI an Inspector appointed by the Secretary of State for Communities and Local Government Date:26th October 2011
PLANNING AND COMPULSORY PURCHASE ACT 2004
SECTION 20
REPORT ON THE EXAMINATION INTO SOUTH LONDON WASTE PLAN
DEVELOPMENT PLAN DOCUMENT
Document submitted for examination on 21 April 2011
Examination hearings held between 12 July and 19 July 2011
File Ref: PINS/L5240/429/5 Abbreviations Used in this Report
AA Appropriate Assessment C+IW Commercial and Industrial Waste CS Core Strategy DPD Development Plan Document GLA Greater London Authority LDS Local Development Scheme LP Local Plan LSIL Locally Significant Industrial Location MSW Municipal Solid Waste NPPF National Planning Policy Framework PPS Planning Policy Statement PPS10 Planning Policy Statement 10: Planning for Sustainable Waste Management SA Sustainability Appraisal SC Change relating to Soundness SCI Statement of Community Involvement SCS Sustainable Community Strategy SDS Spatial Development Strategy SIL Strategic Industrial Location SLWP South London Waste Plan TPA Tonnes per annum
-1- The Councils of the London Boroughs of Croydon, Kingston-upon-Thames, Merton & Sutton South London Waste Plan DPD, Inspector’s Report XXXX 2011
Non-Technical Summary
This report concludes that the South London Waste Plan Development Plan Document provides an appropriate basis for the planning of the area of the four boroughs over the next 10 years. The Councils have sufficient evidence to support the strategy and the sites and areas identified and can show that it has a reasonable chance of being delivered.
A number of changes are needed to meet legal and statutory requirements. The main changes can be summarised as follows:
Comprehensive review and replacement of Tables 3.1 and 3.2 with consequential amendments to policy WP1 to reflect more up-to-date information on waste arisings, waste apportionments and existing waste management capacity derived mainly but not solely from work for the London Plan made available after pre-submission publication of the South London Waste Plan to ensure that the Plan is founded on a robust evidence base; Amendments to policy WP2 and the supporting text to remove any uncertainty as to the wastes addressed by the policy and ensure consistency of interpretation with the London Plan regarding waste management; Amendments to the wording of policy WP3 and the associated Schedule to widen the scope of the sites safeguarded to ensure general conformity with the London Plan; Significant alteration to policy WP5 to acknowledge that it is the policy through which the flexibility of the South London Waste Plan to provide capacity on a contingency basis for municipal, commercial and industrial waste requirements and facilities for other wastes. Changes to clarify its scope, bring various of the criteria into accordance with national policy and make it less restrictive. These changes are required to ensure that the South London Waste Plan is effective in delivery; The deletion of Site 651-Plough Lane which was included as a result of a flawed application of an otherwise robust scoring framework thus ensuring that the identified sites and areas are justified by the evidence base; and The introduction of an entirely new monitoring framework which identifies targets and trajectories, how performance against them will be measured, the management actions that will be considered and the triggers for that consideration. These changes are required to ensure that the South London Waste Plan is effective in delivery
All of the changes recommended in this report are based on proposals put forward by the Partnership Councils in response to points raised and suggestions discussed during the public examination. The changes do not alter the thrust of the Partnership Councils’ overall strategy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.