Resolved

RESOLVED that: 1. it is agreed that the extension of time is no longer required and that Thames Water (TW) should be requested to complete the works by no later than 4October 2012 2. appropriate action is taken to enforce the planning position if the revised timetable put forward by Thames Water and its contractors to foreshorten the period for completion of the works in the light of these changed circumstances, fails to materialise.
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Planning Committee

Summary

This report informs Members of the change in circumstances since it agreed on 21 July 2011 to vary the terms of the S106 legal agreement in respect of the Hogsmill Sewage treatment Works (STW) environmental enhancement works. At that meeting Members agreed to defer the period for the completion of these works by 12 months until 4 October 2012, in order to protect the wider interests of delivering the LDF Core Strategy and the Hogsmill Masterplan as a whole

Recommendations

It is recommended that:

1. it is agreed that the extension of time is no longer required and that Thames Water (TW) should be requested to complete the works as soon as reasonably practicable. 2. appropriate action is taken to enforce the planning position if the revised timetable put forward by Thames Water and its contractors to foreshorten the period for completion of the works in the light of these changed circumstances, fails to materialise.

Reason for recommendations

To complete the outstanding S106 environmental enhancement works as soon as reasonably practicable

Background

1. At its meeting on 21 July 2011, this Committee authorised a variation to the S106 legal agreement to extend the period for completion of the environmental enhancement works to the Western Lagoon at the Hogsmill Sewage Treatment Works by 12 months until the 4 October 2012.

2. This was to protect the wider interests of the delivery of the Core Strategy and the Hogsmill masterplan as a whole and, specifically, to allow time to progress a partnership agreement, under the terms of which technical and ecological impact assessments could be undertaken in order: • To determine whether the lagoon would pose a potential flood risk to the housing proposed in the Masterplan on adjacent TW land fronting Lower Marsh Lane and, if so, • To identify measures that could be undertaken to minimise or mitigate this risk or investigate an alternative location to provide an area of standing water as part of the detailed masterplanning of the area.

3. It was considered sensible to postpone the works to ensure that abortive works and expenditure were not undertaken that might prejudice bringing forward a viable Hogsmill masterplan and thus prejudice the outcome of the Core Strategy and the risks of it being found ‘unsound’ at the EiP

4. The situation has changed since the Committee made its decision on 21 July 2011 as follows:

• The Inspector’s report has been received following the EiP and his binding recommendation is that the Hogsmill Valley should be taken forward as a general designation, otherwise referred to as a ‘broad location’. In the light of this, proposals for the Hogsmill Valley area will be worked up through preparation of a future Development Plan Document.

• A TW/RBK Officer meeting was held in early November when TW:

a) Accepted that the area referred to the Western Scrub was not an option to be pursued for a new student housing development b) Advised that it was not appropriate to pursue the residential strip in Lower Marsh Lane as it would raise insufficient value to mitigate odour risk. c) Advised that TW shareholders were now taking a longer term view and seeking a longer term sustainable approach to managing TW assets rather than regarding asset disposal as its key activity.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HOGSMILL SEWAGE TREATMENT WORKS: S106 LEGAL AGREEMENT ENVIRONMENTAL ENHANCEMENT WORKSReport 87 KB DownloadRead as text

At this meeting

Whole meeting
15MINUTESDecided 17PLANNING APPLICATIONSDecided 17b3-5 Penrhyn Road, Kingston Upon Thames, KT1 2BTAgreed
18HOGSMILL SEWAGE TREATMENT WORKS - S106 LEGAL AGREEMENT ENVIRONMENTAL ENHANCEMENT WORKSThis decision

Who was there

9 of 9 attended
VH
Councillor Vicki HarrisChair, present
GA
Councillor Geoff AustinMember, present
DC
Councillor David CunninghamMember, present
FM
Councillor Frances MoseleyVice-Chair, present
DR
Councillor David Ryder-MillsMember, present
KS
Councillor Ken SmithMember, present
CH
Councillor Chrissie HitchcockMember, present
RH
Councillor Richard HudsonMember, present
MS
Councillor Malcolm SelfMember, present

On this subject at Kingston upon Thames

Search all
  1. HOGSMILL SEWAGE TREATMENT WORKS - S106 LEGAL AGREEMENT ENVIRONMENTAL ENHANCEMENT WORKSThis decision
  2. Odours from the hogsmill sewage works petitionNoted

More from Kingston upon Thames Planning Committee

All decisions
MeetingDecisionOutcome
1 Apr 2026 25/02172/FUL Regent Wing Galsworthy Road Kingston Upon Thames KT2 7QBRESOLVED to DEFER the application for future consideration by the Planning Committee pending discussions with the app... Deferred Open
11 Mar 2026 25/01660/OUT Hobkirk House, 106 Blagdon Road, New Malden, KT3 4BDRESOLVED to PERMIT subject to: 1) The conditions set out in the report, as amended by the Late Material, including su... Approved Open
23 Apr 2025 24/01674/FUL: 4 Manorgate Road, Kingston Upon Thames KT2 7ELRESOLVED to PERMIT subject to: 1) The conditions set out in the report as amended by the Late Material and the Commit... Agreed Open
26 Mar 2025 24/020/71/CREG3: Murray House, 142 Acre Road, Kingston Upon Thames, KT2 6EERESOLVED to PERMIT subject to: The conditions set out in the report as amended by the Late Material, including such a... Decided Open
26 Mar 2025 24/02850/FUL: Chessington World of Adventures Resort, Leatherhead Road, Chessington, KT9 2NERESOLVED to PERMIT subject to the: 1) conditions set out in the report as amended by the Late Material, including suc... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies