AGREED that 1. the Council elects to join the ‘common’ (LoPS) aligning itself with TfL and other London Boroughs to operate its Permit Scheme. 2. an application is made to the Secretary of State for Transport to introduce a Permit Scheme to manage Street works and Road works in the borough. Reason for decision To enable the Council to have the most appropriate, robust powers in place to manage Street works and Road works throughout the Borough.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
The Council has a duty under Section 59 of the New Roads and Street Works Act 1991 (NRSWA) to manage and coordinate all works on the Public Highway; including those of the Utility Companies and those carried out by the Council, its agents and contractors.
The Traffic Management Act 2004 (TMA) imposed a ‘Network Management Duty’ on all Councils to ‘expedite the movement of all traffic on the public highway’.
The London Permit Scheme (LoPS) is made under the TMA ’04 and Traffic Management Permit Schemes Regulations 2007 and gives authorities increased powers to manage works on the public highway. Approval has to be gained from the Secretary of State for inclusion in the Permit Scheme.
LoPS is a ‘common’ permit scheme with each authority managing their own permit scheme under a common set of rules and is now operated by TfL and 27 London Boroughs.
This Council had awaited the report on the success of the LoPS in other boroughs before electing to apply to operate such a scheme. The relative success of LoPS outlined in the review report, along with other considerations, now make joining the LoPS advantageous to Kingston.
Action proposed by the Executive Member for Sustainable Place
It is proposed that:
1. the Council elects to join the ‘common’ London Permit Scheme (LoPS) aligning itself with TfL and other London Boroughs to operate its Permit Scheme.
2. an application is made to the Secretary of State for Transport to introduce a Permit Scheme to manage Street works and Road works in the borough.
Reason for action proposed
To enable the Council to have the most appropriate, robust powers in place to manage Street works and Road works throughout the Borough.
Background
1. Highway Authorities have a duty to coordinate all works on the highway under the New Roads and Street Works Act 1991 (NRSWA). Under these regulations Statutory Undertakers (SUs - usually Utility Companies) are required to notify the Highway Authorities when they need to undertake repairs or improvements to their apparatus. NRSWA provides limited powers to the Council – as Highway Authority – to control the timing and the way in which these works are completed.
2. The Traffic Management Act 2004 (TMA) places a Network Management Duty on all highway Authorities in England. This duty is defined in Section 16(1) of the TMA:
‘It is the duty of the local traffic authority to manage their road network with a view to achieving, so far as may be reasonably practicable having regard to their other obligations, policies and objective, the following objectives:
i.) Securing the expeditious movement of traffic on the authority’s road network; and ii.) Facilitating the expeditious movement of traffic on road networks for which another authority is the traffic authority.’
3. Under part 3 of the TMA, highway authorities can apply to the Secretary of State to operate a Permit Scheme as an alternative to the ‘notification system’ of NRSWA. Under the TMA the Secretary of State also reserves the right to instruct an Authority to operate a Permit Scheme.
4. Permit schemes differ from existing powers for managing activities on the street in a number of key respects:
I. Rather than informing the Highway Authority of their intentions, Statutory Undertakers (SU’s) will need to ‘book’ occupation of the highway for specified periods and for a specified purpose, II. Conditions which impose constraints on the dates and times of activities and the way in which the work is carried out can be attached to permits by the Highway Authority, III. The Highway Authority’s control over variations to the permit conditions, particularly time extensions, should give a greater incentive to complete activities on time.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.