2012/13 LOCAL IMPLEMENTATION PLAN (LIP) FUNDING SETTLEMENT
DecidedCommittee1 paper
the Borough Neighbourhood Committee decided this item on Tuesday 7 February 2012. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the LIP Funding settlement is endorsed (including the reallocations set out above) to enable officers to commence delivery of the 2012/13 programme. Reason for the decision To commence delivery of the 2012/13 LIP programme and to provide any comments to the Place and Sustainability Committee.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Transport for London (TfL) announced RBK’s LIP Funding settlement for 2012/13 on 15 December 2011. This reflects the full amount requested in RBK’s application to TfL as seen and endorsed by the Neighbourhood Committees in June and July 2011 and the Place and Sustainability Committee on 27 September 2011.
In addition, TfL announced funding for Tolworth Broadway (Major Scheme) and a number of Principal Road Maintenance Schemes.
Recommendation
It is RECOMMENDED that the LIP Funding settlement be endorsed, with the amendments set out in paragraph 10, to enable officers to commence delivery of the 2012/13 programme. Any Member comments will be provided to the Place and Sustainability Committee on 20 March 2012.
Reason for recommendation
To commence delivery of the 2012/13 LIP programme and to provide any comments to the Place and Sustainability Committee.
Background
1. On 7 October 2011, RBK officers prepared a LIP funding submission to Transport for London (TfL) for the 2012/13 financial year. (TfL wrote to RBK earlier in the year to advise on the level of funding available, and RBK officers prepared a programme of schemes within this budget limit in accordance with TfL’s LIP Guidance).
2. The schemes all sit within the framework of the Borough’s approved Second Local Implementation Plan (LIP2). The 2012/13 Programme represents Year 2 of RBK’s LIP2 Programme of Investment.
3. The RBK LIP funding proposal for 2012/13 was endorsed by the Neighbourhood Committees in June and July 2011 and the Place & Sustainability Committee on 27 September 2011.
4. This report sets out what RBK’s approved 2012/13 LIP budgets are.
5. The LIP funding received from TfL will support a range of local transport improvements including the Tolworth Broadway Major scheme, a number of Strategic Corridor improvements, cycling and walking schemes, bus stop accessibility, various neighbourhood engineering schemes which address local safety and accessibility, Smarter Travel initiatives and Principal Road maintenance. ANALYSIS OF LIP SETTLEMENT
6. This Committee is requested to acknowledge and endorse the finalised LIP funding allocations made by TfL. This will ensure that officers can commence preparation of scheme development and implementation of the 2012/13 Programmes on or before 1 April 2012 to ensure full delivery and financial spend by 1 April 2013.
7. A summary of the LIP budgets as awarded by TfL for 2012/13 are shown in Table 1 and Figure 1.
Table 1:Summary of LIP Programme Settlement for 2012-13
TfL LIP Programme 2012-13 Allocation Comments Heading Corridors, £1,544k Funding will be used to deliver a Neighbourhoods and range of schemes as endorsed by Supporting Measures the Place and Sustainability Programme Committee on 27 September 2011. See Annex 1 for a full scheme list.
Local Transport Funding £100k This programme area has been retained (Borough Discretionary budget), and will be used to deliver a range of schemes as endorsed by the Place and Sustainability Committee on 27 September 2011. See Annex 1 for a full scheme list.
Principal Road £450k This allocation has been awarded to Maintenance Programme (slightly higher than RBK on the basis of condition reported to Committee surveys undertaken for RBK/TfL. previously) Funding is ring-fenced for the Borough’s Principal Roads only. See Annex 1 for a full scheme list.
Major Schemes £2,010k This budget has awarded entirely for Programme the Tolworth Broadway Greenway scheme and represents an increase in Major Scheme funding from the previous financial year. This will enable the completion of this high profile scheme by the end of 2012/13.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow the Borough Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.