Agreed that 1. the LIP Funding settlement is endorsed with the amendments set out in paragraph 7 to enable officers to commence delivery of the 2012/13 programme; 2. the attention of the London Mayor is drawn to the problems caused by the absence of funding for secondary road maintenance on bus routes; 3. the points made on the Tolworth Greenway project on remaining concerns relating to safety issues were noted; and further information will be reported to the Neighbourhood Committees as appropriate. Reason for decision To commence delivery of the 2012/13 LIP programme on or before 1 April 2012.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Transport for London (TfL) announced RBK’s LIP Funding settlement for 2012/13 on 15 December 2011. This reflects the full amount requested in RBK’s application to TfL as seen and endorsed by the Neighbourhood Committees in June & July 2011 and the Place and Sustainability Committee on 27 September 2011.
In addition, TfL announced funding for Tolworth Broadway (Major Scheme) and a number of Principal Road Maintenance Schemes.
Action proposed by the Executive Member for Place and Sustainability
It is proposed that the LIP Funding settlement is endorsed with the amendments set out in paragraph 7 to enable officers to commence delivery of the 2012/13 programme.
Reason for action proposed
To commence delivery of the 2012/13 LIP programme on or before 1 April 2012.
Background
1. On 7 October 2011, RBK officers prepared a LIP funding submission to Transport for London (TfL) for the 2012/13 financial year. (TfL wrote to RBK earlier in the year to advise on the level of funding available, and RBK officers prepared a programme of schemes within this budget limit in accordance with TfL’s LIP Guidance).
2. The RBK LIP funding proposal for 2012/13 was endorsed by the Neighbourhood Committees in June and July 2011 and the Place & Sustainability Committee on 27 September 2011.
3. The schemes all sit within the framework of the Borough’s approved Second Local Implementation Plan (LIP2). The 2012/13 Programme represents Year 2 of RBK’s LIP2 Programme of Investment.
4. TfL approved the Borough’s LIP programme for 2012/13 in December 2011, and this report sets out what RBK’s approved 2012/13 LIP budgets are.
5. The LIP funding received from TfL will support a range of local transport improvements including the Tolworth Broadway Major scheme, a number of Strategic Corridor improvements, cycling and walking schemes, bus stop accessibility, various neighbourhood engineering schemes which address local safety and accessibility, Smarter Travel initiatives and Principal Road maintenance. 6. The Neighbourhood Committees endorsed the settlement in February 2012. The resolutions from these Committees are set out in paragraph 13-17. Details of the resolutions agreed by the South of the Borough Committee are set out in Paragraph 7 below.
7. The South of the Borough Committee considered a report at the meeting on 7 December regarding the improvement scheme in Leatherhead Road associated with the expansion and rebuilding of Ellingham Primary School. The Committee heard that there was a budget shortfall of £30k and resolved that £20k of this would be obtained by re-allocating the 2012/13 allocation for Clayton Road to the Leatherhead Road scheme. The Clayton Road scheme was successfully completed in 2011/12. It was resolved that the £10k was covered by reducing the 2012/13 budget for Tolworth Girls from £30k to £20k.
ANALYSIS OF LIP SETTLEMENT
8. This Committee is requested to acknowledge and endorse the finalised LIP funding allocations made by TfL. This will ensure that officers can commence preparation of scheme development and implementation of the 2012/13 Programmes on or before 1 April 2012 to ensure full delivery and financial spend by 1 April 2013.
9. A summary of the LIP budgets as awarded by TfL for 2012/13 are shown in Table 1 and Figure 1.
Table 1:Summary of LIP Programme Settlement for 2012-13 TfL LIP Programme 2012-13 Allocation Comments Heading Corridors, £1,544k Funding will be used to deliver a Neighbourhoods and range of schemes as endorsed by Supporting Measures the Place and Sustainability Programme Committee on 27 September 2011. See Annex 1 for a full scheme list.
Local Transport Funding £100k This programme area has been retained (Borough Discretionary budget), and will be used to deliver a range of schemes as endorsed by the Place and Sustainability Committee on 27 September 2011. See Annex 1 for a full scheme list.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.