Local Implementation Plan - Funding Application 2013/14
AgreedCommittee3 papers
Kingston Town Neighbourhood Committee agreed this item on Wednesday 13 June 2012. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the prioritised scheme lists included in Annex 1 of the report as amended by Table 2 of the late material are supported REASON FOR DECISION To agree the scheme priorities for consideration by Place and Sustainability Committee on 20 September 2012 Voting: unanimously in favour
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
To agree the scheme priorities for consideration by Place and Sustainability Committee on 20 September 2012.
1. The TfL 2013/14 LIP Annual Spending Submission Guidance was received by the Council on 1 June 2012 after the Committee report had been finalised. The confirmed 2013/14 LIP allocations are shown in Table 1 below:
Table 1: Confirmed 2013/14 LIP allocations for Kingston Programme Original Revised Allocation for Allocation for 2013/14 2013/14 Corridors, Neighbourhoods £1,324k £1,513k and Supporting Measures Local Transport Funding £100k £100k Principal Road n/a £484k Maintenance N.B. An application of £605k should be made (£484k + 25%) Bridge Strengthening n/a Tbc Total £1,424k £2,097k
2. With regard to the Principal Road Maintenance programme the results of the conditions surveys are being assessed and the funding will allocated to schemes when that assessment is complete.
RECOMMENDED 2013/14 PROGRAMME
3. With regard to the additional funding in the Corridors, Neighbourhoods and Supporting Measures programme, the schemes in Annex 1 have been reviewed and the proposed changes are shown in Table 2 overleaf: Table 2
Figure 1 (Revised): Kingston 2013/14 LIP Funding Submission Timetable - June 2012 to April 2013
Date Action Required Action
13 and 20 June 2012 Neighbourhood Committee sign-off of 2013/14 schemes 20 September 2012 Place and Sustainability Committee sign- off of 2013/14 schemes 5 October 2012 TfL Submission Deadline October to December 2012 TfL review submission and discuss any issues arising from this review process December 2012 (tbc) TfL will confirm plans for schemes/intervention delivery to enable RBK to commence planning Early 2013 Neighbourhood committee advised of 2013/14 schemes Early 2013 Place and Sustainability Committee advised of 2013/14 schemes April 2013 2013/14 LIP Programme commences (Year 3 of 3-year LIP2 Programme of Investment)
Additional Background papers: held by John Bolland, Service Manager, Traffic Management & Design – 020 8547 4691, e-mail: [email protected] • TfL 2013/14 LIP Annual Spending Submission Guidance received 1 June 2012
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Kingston Town Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.