RESOLVED THAT - 1. the projected revenue budget outturn for 2012/13 be noted; 2. the forecast capital outturn for 2012/13 be noted; 3. adjustments to the capital programme for 2012/13 to 2014/15 as set out in the report be approved. Reason for Decision To ensure that the 2012/13 revenue expenditure remains within budget. To provide an update on capital expenditure to date and progress against the approved capital programme and agree adjustments to the capital programme for 2012/13 to 2014/15. Voting - Unanimous
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
1. The report summarises the Council’s projected revenue budget outturn for 2012/13 as at Month 10 and explains significant variances.
2. The report provides a summary of the Capital Programme for the current financial year and the latest monitoring information relating to its delivery as at month 10 2012/13.
3. The report also seeks approval for a number of minor additions to the capital programme for 2012/13 and 2014/15.
Action proposed by the Executive Member for Finance and One Council
It is proposed that the Committee
1. note and comment on the projected revenue budget outturn for 2012/13
2. note the forecast capital outturn for 2012/13
3. approve adjustments to the capital programme for 2012/13 to 2014/15 as set out in the report
Reason for action proposed
To ensure that the 2012/13 revenue expenditure remains within budget. To provide an update on capital expenditure to date and progress against the approved capital programme and agree adjustments to the capital programme for 2012/13 to 2014/15.
Background
1. The Council set its financial plan for the year in Destination Kingston 2012-16 and recently approved an updated Destination Kingston for 2013-17; this report charts progress against that plan for 2012/13 both for the revenue budget and the capital programme.
2. The majority of the planned revenue savings will be delivered through the One Kingston programme. Progress on this programme, and on the individual projects within it, is reported separately to the Policy & Resources Committee on a regular basis. The People’s Services and Place & Sustainability Committees also receive regular reports on the major commissioning and service development / transformation projects in those areas which fall within their respective remits and which form part of the overall budget strategy.
3. This report gives details of the projected revenue outturn position and projected capital outturn position for 2012/13 as at month 10 both for the General Fund and the Housing Revenue Account. The report reflects the position at a point in time. Directors and Service Managers are monitoring their budgets and reviewing the position continuously, and using that work to refine forecasts to reflect changes in information available, including activity data. Where appropriate, the ongoing impact of the 2012/13 revenue position has been taken into account in the agreed 2013/14 revenue budget proposals.
4. The month 10 revenue report indicates that based on the latest forecast, the General Fund Revenue Account would under spend by £0.024m at year end. Should this prove to be the case then the General Fund Balance would increase from £7.157m to £7.181m. The current expectation is that ongoing management of the position will result in a break even position to small under spend at year end.
5. The Housing Revenue Account (HRA) is projected to be over spent by £0.212m which would reduce the HRA balance from £3.145m to £2.933m.
REVENUE - GENERAL FUND FORECAST OUTTURN 2012/13
6. The overall General Fund forecast 2012/13 at month 10 is summarised in the following table. Further details can be seen in Annex 1. Month 6 Month 10 2012/13 2012/13 Forecast 2012/13 Forecast Outturn 2012/13 Forecast Outturn Variance Budget Outturn Variance Function £000s £000s £000s £000s Adult Social Care (107) 51,936 52,333 397 Learning & Childrens Services 555 36,689 37,334 645 Place (709) 28,473 27,955 (518) Total Functions (261) 117,098 117,622 524 One Council Services (ICT & Assets) 242 (527) (495) 32 One Council Services (Strategic Business) 66 5,626 5,424 (202) One Council Services (Finance) 68 7,773 7,755 (18) Total One Council Services 376 12,872 12,684 (188) Neighbourhoods 0 6,383 6,383 0 Other Corporate Services (88) (1,614) (1,974) (360) Total Other Functions (88) 4,769 4,409 (360)
Total General Fund 27 134,739 134,715 (24)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy and Resources Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Safer Kingston Partnership Plan 2014/17RESOLVED TO RECOMMEND TO COUNCIL that – 1. the Partnership Plan attached at Annex 1 to the agenda and, pursuant to Re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.