RESOURCE PLAN

Noted Committee 1 paper

South London Waste Partnership Joint Committee noted this item on Thursday 25 April 2013. Below is the council's own wording, with the papers it was decided on.

Item50

Resolved

RESOLVED that 1. the new structure is noted and recruitment to the following posts approved on a flexible salary and term basis a) Project Support Officer. b) Contract Data Officer. c) Programme Manager 2. the Contract Manager post approved at the last meeting is recruited to on a similarly flexible basis as regards term and salary Reason for decision To provide appropriate resourcing to the Partnership to continue its necessary work throughout 2013/14 and 2014/15.
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to South London Waste Partnership Joint Committee

Summary

The last Joint Waste Committee meeting agreed a new Partnership structure that would operate until the end of June 2013.

The Management Group has developed a new structure designed to meet the Partnership’s resource requirements beyond June 2013, which is presented in this paper.

Recommendations

It is recommended that

1. The Joint Waste Committee note the new structure.

2. The Joint Waste Committee approve the recruitment of the following posts:

a) Project Support Officer, two year fixed-term appointment. b) Contract Data Officer, two year fixed-term appointment. c) Programme Manager, two year fixed-term appointment.

Reason for action proposed

To ensure the Partnership is appropriately resourced and able to continue its necessary work throughout 2013/14 and 2014/15.

INTRODUCTION

1. At the last JWC, a structure was agreed to operate to June 2013. It was noted that this resource plan needed to be extended to consider resource requirements beyond June 2013 and to propose a structure to meet these requirements.

2. This action has been progressed by the Management Group and following discussions a new structure is proposed for 2013 – 2015.

3. This new structure requires the recruitment of three posts. One of these is an amendment to an existing post while the other two posts are new.

4. The Partnership has applied a programme management approach to consider how best to provide the resources required for the Partnership’s future Work Programme. RESOURCE PLANNING

5. At the last JWC, the activities included in the Work Programme were summarised as shown below:

- Phase A o Contract management o Contract review o Contract renegotiation and/or procurement

- Phase B o Respond to Planning Decision o Manage potential Satisfactory/Unsatisfactory Planning Decision o Commissioning of the new facility o Development of Contract Management and handover

- Governance o Management of IAA and approach to JWA if appropriate (subject to legislation)

6. The Management Group considered the skills required in order to progress the Work Programme, and based on this the JWC agreed the following structure to operate until June 2013:

Joint Waste Committee

SLWP Governance Meeting Finance Directors’ Meeting

Management Group

Commercial Director Contract Manager

Project Manager

7. Based on further discussions of this structure and taking into account identified resource gaps, the following structure is now proposed to operate until 2015. Joint Waste Committee

SLWP Governance Meeting Finance Directors’ Meeting

Management Board

Programme Manager Contract Manager

Project Support Officer Contract Data Officer

Resource Bank

Incorporating: - Advisers - Commercial - Communications - Finance - Legal - Strategy - Governance - H&S

8. This structure is designed to meet the listed resource requirements and to be flexible to the changing demands on the Partnership.

9. As part of this new structure, consideration is being given to the requirement to create terms of reference for the Management Group. The Management Group’s operation has developed as required over the past ten years to meet changing demands. As a consequence, the Group can cover operational, strategic and contractual requirements in every fortnightly meeting.

10. Clarifying terms of reference and related operating procedures will enable the Group to more effectively manage these demands. In combination with the Governance meeting, this will enhance the strategic focus of the Partnership as it moves into new areas of work in coming years.

11. If this proposal is agreed by the Management Group it will be put to the Joint Waste Committee for agreement. If it is felt that changing the Management Group’s name to “Management Board” will help formalise these changes, this will also be proposed. This may require amendments to the Partnership’s IAA and Constitution.

NEW POSTS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
RESOURCE PLANReport 84 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
MB
Councillor Mark BetteridgeMember, present
CH
Councillor Colin HallMember, present
SH
Councillor Sharon HartleyMember, present
SH
Councillor Simon HoarMember, present
AJ
Councillor Andrew JudgeVice-Chair, in the Chair, present
DO
Councillor Derek OsbourneChair, apologies
RR
Councillor Roger RobertsMember, present
PT
Councillor Phil ThomasMember, present

On this subject at Kingston upon Thames

Search all
  1. RESOURCE PLANThis decision
  2. SAFER KINGSTON PARTNERSHIP PLAN 2014/17 [Policy and Resources Committee - 3 April 2014 - Appendix B]Approved
  3. DESTINATION KINGSTON - MEDIUM TERM SERVICE AND FINANCIAL PLAN 2014/15 TO 2017/18 AND DETAILED BUDGET AND COUNCIL TAX 2014/15 [Policy and Resources Committee - 13 February 2014 - Appendix A]Approved
  4. MEDIUM TERM SERVICE AND FINANCIAL PLAN 2013/14 TO 2016/17 (DESTINATION KINGSTON 2013-2017) (Policy and Resources Committee - 14 February 2013 - Appendix D)Decided
  5. DESTINATION KINGSTON - MEDIUM TERM SERVICE & FINANCIAL PLAN 2012/13 TO 2014/15 AND DETAILED BUDGET & COUNCIL TAX FOR 2012/13 - Policy and Resources Committee - 9 February 2012 (Appendix C)Approved

More from Kingston upon Thames South London Waste Partnership Joint Committee

All decisions
MeetingDecisionOutcome
11 Jun 2025 Election of new Chair and Deputy Chair of the committeeRESOLVED that Councillor Christopher Woolmer be elected as Chair for the 2025/26 year. Carried Election of Vice Chair... Decided Open
17 Dec 2020 MinutesThat the minutes of the previous meeting held on 9 September 2020 be confirmed and approved as the correct record. Vo... Approved Open
17 Dec 2020 Partnership Budget Update - Month 6To note the contents of the report. Voting: Unanimous Noted Open
17 Dec 2020 Partnership Budget 2021/22To agree the proposed budget for the core activities of the Partnership. Voting: Unanimous Agreed Open
17 Dec 2020 Communications UpdateTo note the contents of the report. Voting: Unanimous Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies