RESOLVED that the following items are noted: · Potential Forthcoming Business (including the cancellation of the 26 June meeting) · Traffic Schemes updates (The TfL update was tabled) In relation to the scheme at Malden Rushett Crossroads, TfL were requested to meet their June 2013 target date for formal consultation with local residents. In relation to the scheme at Hook Road / Elm Road junction, Members requested that TfL are asked to: a) consider how to reduce the traffic congestion impact of the weekend works which are causing queues reaching back to The Maypole, and thus deterring customers from using the Hook Parade shops. b) return the benches to the Hook Parade c) liaise with the Streetscene team in relation to the relocation of bins to prevent littering at this location · Planning Appeals update · Community Plan update
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
1. Potential forthcoming business 2. Traffic Schemes Updates: (a) RBK schemes (b) TfL TLRN schemes 3. Planning Appeals update 4. Community Plan Update
1. POTENTIAL FORTHCOMING BUSINESS
26 June – (may be cancelled if no Planning Applications – TBC on 31/5) if held- Hook Centre
17 July – Hook Centre • Planning applications • Bolton Road traffic management review • Street Lighting and Illuminated Signs Policy Statement Consultation • Local Implementation Plan • Budget Monitoring report • Information item: Air quality monitoring results
Tuesday 10 September – Tolworth Girls School • Planning applications • Consultation on LDF Gypsy and Travellers’ sites Development Plan Document • Brook Road, Surbiton. Review of experimental residents’ parking zone • Budget Monitoring report • Somerset Avenue traffic management
23 October - Ellingham Primary School
13 November – Hook Evangelical Church
4 December – Chessington Methodist Church • Library fees and charges
15 January 2014 – Hook Centre
5 February 2014 – Hook Centre • 2014/15 Budget Report
5 March 2014 - Ellingham Primary School
2 April 2014 – *Southborough School (awaiting confirmation of availability of this venue)
Item to be scheduled: • Tesco planning application 2. TRAFFIC SCHEMES UPDATES:
(a) RBK SCHEMES
Scheme Current situation Tolworth Works started on 18 March with a planned completion date of mid Greenway September. scheme Ellingham Primary The scheme has been completed except for the installation of anti School skid surfacing on the approach in Merritt Gardens. The SCOOT traffic signal control system was commissioned on 3 May 2013.
Brook Road The experimental residents parking scheme became operational on parking scheme 1st February 2013. Enforcement has now started following a familiarisation period. The scheme will be reviewed approximately six months after the operational date.
Cox Lane Bus Works to amend the lorry ban boundary and improve the signage Gate have been ordered.
Lorry issues in Following the discussions at the April Committee in question time a Hunters Road meeting has been held with TfL to agree measures to reduce the occurrence of lorries turning left into Hunters Road from Hook Road. The issue of lorries approaching the width restriction from the Industrial Estate direction will be reduced when the signage at the bus fate is improved. At that time the Council will write to all businesses on the Industrial Estate to inform them of the Council’s powers to enforce moving traffic contraventions.
Sanger Avenue Following the discussions at the April Committee in question time a parking scheme to stop parking on the east side of the road between Durbin restrictions Road and Cox Lane is being progressed.
Bridge Road TfL’s review of the traffic monitoring data for the Bridge Road roundabout traffic roundabout was considered at the April meeting. TfL to progress the monitoring public consultation on their proposal to make the experimental scheme permanent.
Bolton Road traffic The Committee at the April meeting agreed to form a Working Group management of local residents to carry out a review of the through traffic issues. review The first meeting will take place in week commencing 10 June. Committee will consider a report on progress in July 2013.
Somerset Avenue Local residents have again expressed concern about the volume of traffic through traffic using the Somerset Avenue area. An initial meeting management was held with residents last year when a number of people agreed to review be a member of a Working Group. The notes from that meeting have been circulated. The first meeting of the Working Group took place on 14 May and a report is on this agenda to agree the terms of reference. Thornhill Road The agreed scheme has been completed. improvement scheme Angus Close The scheme to introduce a section of footway parking exemption and rearrangement of the road markings is complete.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow the Borough Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.