Resolved
RESOLVED that the performance monitoring report is noted. Reason for decision To confirm the Committee remains aware of the current performance of the Partnership’s Phase A contracts and action being taken where appropriate.
South London Waste Partnership Joint Committee noted this item on Tuesday 18 June 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the performance monitoring report is noted. Reason for decision To confirm the Committee remains aware of the current performance of the Partnership’s Phase A contracts and action being taken where appropriate.
This report advises the Joint Waste Committee of the performance of the three Phase A contracts applicable to the South London Waste Partnership (“the Partnership”), which have been operational since September 2008.
It is recommended that
The Joint Waste Committee is asked to note the contents of this report, and to comment on any aspects of the performance of the Partnership’s Phase A contracts.
Reason for action proposed
To ensure the Committee remain aware of and are satisfied with the current performance of the Partnership’s Phase A contracts.
Background / Introduction
1. This paper provides a quarter 4 update on the performance of the three Phase A contracts for the financial year 2012/13. These contracts have been in place and operating since 2008.
Contract 1 Landfill and Transportation. Contract 2 Management of House Hold Reuse and Recycling Centres. Contract 3 Materials Recycling Service, Composting and additional Treatment Service
2. Contracts 1 & 3 are operated by Viridor Waste Management LTD.
3. Contract 2 is operated by Environmental Waste Controls (EWC).
CONTRACT MANAGEMENT
4. The London Borough of Sutton continued to undertake the contract management function on behalf of the Partnership up until the end of March 2013. This provided the additional resource required to manage the contracts and provides capacity to focus on commercial as well as operational management. The reviewed contract management structure has continued to develop.
5. Moving forward, the Partnership plan to recruit into this position. A job description and person specification has been finalised and the Royal Borough of Kingston undertook to evaluate the role and subsequent advertisement on behalf of the Partnerships. Interviews were held in April, but unfortunately no suitable candidate was appointed.
6. Since April the London Borough of Croydon have resumed the responsibility on an interim basis for contract management and a considerable amount of time has initially been spent on working with EWC to resolve some significant operational issues specifically at the three Croydon sites.
7. The Phase A contract review has continued. To date this work has focused on driving down the gate fee for general waste and removing the gate fee and associated cost for the dry recycling and implementing a profit sharing paymech from the sale of material. Financial assessments and an impact analysis has been conducted in order to support management group in making informed recommendations.
8. In line with these arrangements monthly briefing notes are produced updating the Partnership on all current work streams. In addition to this a quarterly performance monitor has been produced linking both financial and operational areas of performance. (See Appendix 1).
DETAIL
CONTRACT 1 – LANDFILL AND TRANSPORTATION (VIRIDOR WASTE MANAGEMENT LTD.)
9. The contract is operating effectively with municipal solid waste delivered to Viridor’s Beddington Farmlands Landfill facility by all Partnership boroughs.
10. Viridor continued to operate in line with the contract and there were no operational issues reported.
11. There is no performance or formal complaint issues relating to this contract.
CONTRACT 2 – MANAGEMENT OF HOUSEHOLD REUSE & RECYCLING CENTRES (ENVIRONMENTAL WASTE CONTROLS)
12. EWC continues to perform well in respect of the diversion of household waste from landfill for reuse and recycling when compared to pre contract recycling rates and current contractual targets.
13. Over the last half of the year EWC have found it challenging to build on last year’s recycling performance when compared to the same period last year.
14. In order to assist in the recycling performance monitoring EWC has implemented real time recycling updates. This is to enable the supervisors to direct their attention where needed across the sites in order to maintain service performance targets.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Phase A Contract Management: Appendix 1Appendix | 312 KB | Download |
PDF |
Phase A Contract ManagementReport | 60 KB | DownloadRead as text |
Follow South London Waste Partnership Joint Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Jun 2025 | Election of new Chair and Deputy Chair of the committeeRESOLVED that Councillor Christopher Woolmer be elected as Chair for the 2025/26 year. Carried Election of Vice Chair... | Decided | Open |
| 17 Dec 2020 | MinutesThat the minutes of the previous meeting held on 9 September 2020 be confirmed and approved as the correct record. Vo... | Approved | Open |
| 17 Dec 2020 | Partnership Budget Update - Month 6To note the contents of the report. Voting: Unanimous | Noted | Open |
| 17 Dec 2020 | Partnership Budget 2021/22To agree the proposed budget for the core activities of the Partnership. Voting: Unanimous | Agreed | Open |
| 17 Dec 2020 | Communications UpdateTo note the contents of the report. Voting: Unanimous | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.