RESOLVED that 1. the report is noted, the Terms of Reference for the Working Group as shown in Annex 1 are endorsed, and work is progressed on the proposals set out in paragraphs 6, 7 and 8, to enable a public consultation to be carried out ; and 2. authority is delegated to the Head of Planning and Transport, in consultation with the Chair, Vice Chair and Ward Members, to take forward the Working Group’s selected proposals for public consultation, the outcome of which will be reported to the Committee for decision at its November meeting. Reason for the decision To endorse the way forward for the new Working Group in identifying and progressing a solution to the issues of most concern to the residents of the area. Voting - unanimous
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
The Committee on 17 April 2013 agreed to the formation of a Working Group to consider the through traffic issues in the Bolton Road area (see ANNEX 2). The first meeting of the Working Group has taken place and this report provides a summary of the discussion and outcomes from that meeting. The next stage will be to consult the local community on the possible improvement schemes and the results will, be reported to a future meeting of the Committee.
The Committee on 17 April 2013 received a report on the outcome of the Transport for London (TfL) review of the A243 Bridge Road roundabout experimental scheme. TfL at that time favoured making the current scheme permanent. The Committee requested that TfL consults widely on the proposal. RBK Officers have had discussions with TfL and they now consider the best approach to be a full review of the roundabout. The experimental scheme will stay in place whilst the study and any new scheme is developed. This means that the through traffic issue in the Bolton Road area is likely to continue during the intervening time. If the Commixes agrees to consult on the Bolton Road area options, the process will not be complicated by the Bridge Road roundabout situation.
Recommendations
It is RECOMMENDED that
1. the report is noted, the Terms of Reference for the Working Group as shown in ANNEX 1 are endorsed, and work is progressed on the proposals set out in paragraphs 6, 7 and 8, to enable a public consultation to be carried out; and
2. authority is delegated to the Head of Planning and Transport, in consultation with the Chair, Vice Chair and Ward Members, to take forward the Working Group’s selected proposals for public consultation, the outcome of which will be reported to the Committee for decision at its November meeting.
REASON FOR RECOMMENDATION To endorse the way forward for the new Working Group in identifying and progressing a solution to the issues of most concern to the residents of the area.
Background
1. The Committee considered a report on 4 July 2012 relating to through traffic issues in the Bolton Road area. That report provided the results of traffic surveys and outlined the factors that have influenced the change in traffic pattern in the Bolton Road area over recent years. The most significant factor was the changes Transport for London (TfL) made in November 2009 on the A243 at Bridge Road roundabout and the Hook Road approach. The 4 July 2012 Committee meeting agreed that action on the Bolton Road area traffic issues should be deferred until the outcome of a review of the TfL A243 roundabout scheme had been completed. 2. On 17 April 2013 the Committee considered a report that provided the results of the TfL review of the A243 roundabout scheme. TfL Officers attended the meeting to explain the outcome and answer questions. At that time TfL favoured making the experimental scheme permanent. Having reached this point, it was appropriate for the Committee to agree to the setting up of a Working Group of representatives from the Bolton Road area. The Committee made the following resolutions on 17 April 2013: 1. the Transport for London monitoring review report is noted; 2. Transport for London is requested to consult the local community on their proposal to make the experimental scheme permanent and the results of the consultation are reported to a future meeting of the Committee; and 3. a working group is formed (including Ward Members, the Committee Vice Chair, and residents of the Bolton Road area) to consider the traffic management issues in their area related to through traffic and the group reports to Committee at each stage of the process
WORKING GROUP
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow the Borough Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.