RESOLVED that – 1. the preferred option from the Commissioning Options Appraisal exercise (Option 3: Total Facilities Management) be adopted as the preferred model for sourcing Corporate Repairs and Maintenance and Facilities Services for the Council in future; and 2. the Director of Place be authorised to commence a procurement exercise to select a commercial partner to deliver a Total Facilities Management ... view the full minutes text for item 71.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
This report makes recommendations on the future provision of property services within the Place Directorate following consideration through the Council’s commissioning process.
This is one of five priorities within the Place-Shaping programme in the Place Directorate. The report describes the process through which the project has progressed, and the main findings which have led to the recommendations.
The report focuses on examining the existing arrangements for the sourcing, contracting and management of such arrangements. It then identifies where improvements can be made to achieve value for money, cost savings and efficiencies, through the internal and external supply chain.
Action proposed by the Lead Member for Finance and Resources
It is recommended that the Committee agrees to:
1. Adopt the preferred option from the Commissioning Options Appraisal exercise (Option 3: Total Facilities Management) as the preferred model for sourcing Corporate Repairs and Maintenance and Facilities Services for the Council in future; and
2. Delegate authority to the Director of Place to commence a procurement exercise to select a commercial partner to deliver a Total Facilities Management solution for the Council, subject to a final Tender Award report being ratified in due course, before new contract arrangements commence from April 2015.
Reason for action proposed
To enable the re-commissioning of services in line with the Council’s approach to commissioning and deliver cost savings in line with the Medium Term Financial Plan and to improve the performance of property related services in line with the Assets Strategy 2013 – 2018. Background
1. The vision for Kingston the place is to be the best possible place to live, work, and visit; to be the destination of choice; and one that offers an easily identifiable experience for every corner of the Borough – it’s a great place to be for free. A vision which is derived from the Council’s medium term service and financial plan – Destination Kingston.
2. In order for us to deliver this vision we have established a programme (the ‘Place Shaping programme’) covering a range of activity, which primarily focusses upon the Council’s commissioning framework. This programme is one of five Priority work streams and is a re-commissioning project for a range of services that are currently provided within the Corporate Landlord group of services. The report recommends a commissioning approach based upon a detailed business case (copies of which are available upon request as a background paper).
3. The Priority 5 Programme has been developed in line with the established corporate commissioning process, underpinned by robust project management. It also integrates the Kingston Test and existing Place Directorate and Property Services governance arrangements. It follows on from the adoption of the One Council Corporate Landlord function undertaken as part of One Council programme (Project 5 - OCP5), the precursor to the current One Kingston programme.
4. This programme is being developed in two phases. The first phase focuses on risks and issues within the Corporate Landlord Service which must be addressed as priority. These primarily relate to the current arrangements for sourcing Facilities Management, Repairs and Maintenance, and other property related services both from within the Council and from the open market. The second phase deals with the overall restructuring of the Corporate Landlord Service so that it is better aligned with the Council’s wider strategic, financial and organisation change priorities. This paper deals with phase one of the programme.
Programme objectives
5. The programmes’s objectives are:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy and Resources Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Safer Kingston Partnership Plan 2014/17RESOLVED TO RECOMMEND TO COUNCIL that – 1. the Partnership Plan attached at Annex 1 to the agenda and, pursuant to Re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.