Resolved
RESOLVED that 1. the Residents’ Petition submitted on 15 January 2014 is noted, ... view the full minutes text for item 8.
the Borough Neighbourhood Committee noted this item on Wednesday 5 March 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that 1. the Residents’ Petition submitted on 15 January 2014 is noted, ... view the full minutes text for item 8.
SOUTH OF THE BOROUGH NEIGHBOURHOOD COMMITTEE
5 MARCH 2014
RESPONSE TO THE CLAYTON ROAD PETITION REGARDING THE EQUESTRIAN CENTRE DEVELOPMENT
REPORT BY THE HEAD OF PLANNING AND TRANSPORT
LATE MATERIAL
A meeting took place on Wednesday 26 February between Edward Davey MP, Surrey County Council (SCC) Highway Engineers, the Owner of Chessington Equestrian Centre, the Contractor for the Equestrian Centre Development, Chessington District Residents Association (CDRA), Ward Members and RBK’s Neighbourhood Traffic Engineer to discuss alternative construction accesses for the re-development of the Equestrian Centre.
The two access points leading to and from the A309 to the north of the Equestrian Centre site had been cleared by the owner prior to the meeting. The Contractor presented a case for using both these accesses, including an offer to undertake accommodation works to lessen the gradients leading to and from the site. SCC had highway safety concerns regarding these accesses, mainly because of insufficient entry/exit slip roads (taper lanes). Achieving these to SCC’s required standards would be prohibitively expensive and probably not feasible owing to the proximity of the over-bridge to the main A3. Edward Davey asked to be provided with the design guidance used by SCC so that he could fully understand this issue. SCC pointed out that, in any event, a planning application would need to be made to Elmbridge District Council, (and referred to SCC as Highway Authority), and a S278 Agreement entered into with SCC. The Contractor wished to avoid the prospect of any further delays whilst these processes were gone through. They expressed concern that if works could not progress soon, the project would be delayed by a year jeopardising the viability of the Equestrian Centre.
CDRA suggested two further alternatives. The first was an access through the allotment site to the section of the A309 within the Kingston Borough Boundary, which is part of TfL’s Transport for London Road Network (TLRN). This had previously been discussed between RBK officers and the Allotment Society. However, when the assembled group looked at this point of access when viewed from the A309, there was agreement that it was not feasible owing to poor visibility and the speed of traffic. Also, coning off a lane for 18 months to overcome these problems was seen as an unreasonable requirement that TfL would be unlikely to agree to.
The second suggestion from CDRA was to take exiting vehicles from the Equestrian Centre directly eastwards across the Hook Road Allotment Site, across the Rugby Club Site (King Edward Recreation Ground) and out through the existing access road onto the A243 Hook Road. It was acknowledged that there would be issues with this in terms of conflicts with other uses involving pedestrians and children. Also, it would require two planning applications to be submitted to RBK. One for the engineering operations in connection with the hardstanding required for access across this land and a second application to vary condition 3 of the original permission which explicitly states the egress routes to be used by these vehicles during construction. Both of these applications would be given target determination periods of 8 weeks. Any consultation on these applications would involve the nearby properties including the St Paul’s Parish Hall, the Rugby Club, the Allotment Society, the Hook Scout Group etc. and objections would be likely. Also, as Hook Road is on the TLRN, TfL would need to be consulted.
The Contractor saw this last suggestion as offering a way of avoiding the use of Clayton Road. Following the meeting, they also suggested that this could be used as an entry route as well as an exit. (RBK’s Traffic Engineers have concerns that the narrow entrance would requiring lorries to approach from the outer lane of the Hook Road causing potential conflicts with vehicles in lane one. TfL would need to consider this aspect of the proposal.)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
RESPONSE TO THE CLAYTON ROAD PETITION REGARDING THE EQUESTRIAN CENTRE DEVELOPMENTReport | 69 KB | Withheld: personal details |
PDF |
xEquestrian Centre Late MaterialReport | 51 KB | DownloadRead as text |
PDF |
xLateMaterialroutestofromChessingtonEquestrianReport | 341 KB | Download |
Follow the Borough Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | Community grant applicationsRESOLVED that: 1. the application for a £3,000 Neighbourhood Community Grant from Voices of Hope, as set out in parag... | Approved | Open |
| 11 Jun 2026 | Appointment of Chair and Vice-Chair for 2026/27 Municipal YearIt was RESOLVED that; 1. Councillor Lorraine Dunstone be appointed Chair of the Committee for the Municipal Year 2026... | Decided | Open |
| 11 Jun 2026 | Objections to double yellow lines- Compton Crescent, Marston Avenue, Elmcroft Drive, Bridge Road junction with Leatherhead road, KnollmeadScheme 1. Elmcroft Drive RESOLVED that – 1 the comments and objections received as set out in paragraphs 2 and 7 and ... | Noted | Open |
| 11 Jun 2026 | Community Grant ApplicationRESOLVE D that – 1. the application for a Neighbourhood Community Grant of £3,000 from New Era Community Projects CIC... | Approved | Open |
| 11 Jun 2026 | Neighbourhood Working Arrangements 2026 - 2030RESOLVED that – 1. Planning Sub-Committee not be established for the 2026-30 municipal term; and 2. that a ‘guillotin... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.