It was therefore agreed that environmental factors such as the type of energy and/or carbon intensity in the generation of the energy should also be taken into account in the new arrangements. It was not possible to precisely define the balance to be applied between price and carbon intensity owing to the fluctuating state of the supply market, but the latter would be a significant factor. The Committee would approve the framework contract but the need for short notice decisions meant that individual purchases would continue to be authorised by Officers in consultation with the relevant Lead Member. The Committee also took the opportunity to receive details of current energy efficiency projects and future carbon reduction initiatives. RESOLVED that – A review of the LASER contract be undertaken by December 2014 that follows a set of guiding principles that will take account of the carbon intensity and the wider environmental implications of energy procurement. Reason for decision The proposed action will ensure a best practice and a risk managed approach to energy procurement. It will provide the opportunity to prioritise energy generated from sources with low carbon emissions thus contributing to reducing the Council’s environmental impact. Voting – Unanimous
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
The council purchases energy from the London and South East Region (LASER) service provider. This is a ‘purchase in advance’ contract that is due to be renewed in 2016 providing the opportunity to review the current purchasing arrangements by the end of 2014. This report discusses the issues around energy procurement within the public sector and recommends a set of outline principles that will be considered when assessing its future energy purchasing strategy.
Action proposed by the Lead Member for Sustainability and Sport
It is proposed that
1. A review of the LASER contract is undertaken by December 2014 that follows a set of guiding principles that will account of the carbon intensity and the wider environmental implications of energy procurement.
Reason for action proposed
The proposed action will ensure a best practice and a risk managed approach to energy procurement. It will provide the opportunity to prioritise energy generated from sources with low carbon emissions thus contributing to reducing the Council’s environmental impact.
Background
1. The Council currently purchases energy (electricity and gas) from LASER. The decision to enter into a 4 year purchase in advance contract was made by this committee in June 2011. LASER is a central purchasing body that buys energy on behalf of its public sector portfolio from a range of energy suppliers on the commercial market.
2. Central energy purchasing bodies such as LASER rely on early client commitment to place into the portfolio. This is normally one year in advance of a two year pre- purchasing plan. Large portfolios are more attractive to suppliers and can attract up to 3% lower prices. LASER started purchasing energy on our behalf during September 2012, and therefore this date was the commencement of the contract.
3. Buying electricity and gas for a Council is not the same as purchasing in the domestic market. Here, suppliers do not pass on the effects of short term volatility in wholesale markets like for a domestic customer. Conversely, Councils can buy on the commercial market directly where prices can move, plus or minus 20% within a month, which is passed onto the purchaser. LASER only purchases energy on behalf of the public sector.
4. When the decision by the committee was taken to use LASER as the council’s central purchasing body price and financial risk management were the core purchasing principles. Environmental impacts such as type of energy and/or carbon intensity was not, at the time, a priority.
5. The purchasing principles are there to meet the energy needs of corporate assets, HRA Housing needs for communal areas (not residential energy use), some schools, and street-lighting. Each category requires different volumes of energy and has different limits to how much financial risk they can be exposed to. This then determines how and when the energy can be purchased from the market and consequently the price that can be secured. The energy purchasing strategy the Council currently uses enables the Council and those responsible for the energy needs of the Council to primarily manage financial budges and exposure to financial risk.
6. The current electricity supplier to Laser’s flexible framework is Npower and the gas supplier to Laser’s flexible framework is Total Gas & Power. Apart from the flexible contracts RBK also has fixed term fixed price (FTFP) contracts in place for smaller quarterly billed supplies. Currently EDF and Southern Electric are the suppliers to these contracts
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Place and Sustainability Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Housing Allocations Policy ReviewIt was therefore agreed that two children of the same sex would now be expected to share a bedroom where they were bo...
Enforcement Policy on Waste and LitterRESOLVED that – 1. the draft attached at Annex 1 to the agenda report be endorsed; 2. the draft policy be reported fo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.