RESOLVED that: 1. the successes of the first year of using LoHAC in Kingston and financial benefits as detailed in the report are noted; 2. it is noted that the contract has enabled additional work, without the requirement for additional funding; and 3. it is noted that there is a series of joint improvement teams working to ensure the contract continues to improve and create benefits for Kingston. Voting: Unanimous.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
1. the successes of the first year of using LoHAC in Kingston and the financial benefits (ref para 23) are noted; 2. it is noted that the contract has enabled additional work, without requirement for additional funding (ref para. 24); and 3. it is noted that there is a series of joint improvement teams to ensure the contract continues to improve and create benefits for Kingston (ref para. 10-11).
Key Points
A. In November 2012, the Council agreed to enter into the Transport for London- sponsored London Highway Alliance Contract (LoHAC) for an eight year period from 1 April 2013 to 31 March 2021.
B. The London Highway Alliance Contract provided a new way of working and potential financial benefits for the Council.
C. When the contract was agreed, there was a requirement to undertake a performance and efficiency review after twelve months to check actual first year cost benefits and to identify any opportunity for more efficiencies.
D. This report presents the first annual performance and efficiency review for Members’ consideration.
E. Financial benefits for Kingston created by the use of the London Highway Alliance Contract are confirmed, as are current risks and mitigation measures.
F. Future plans for the contract and its improvement are presented.
Context
1. On 29 November 2012 the Place and Sustainability Committee agreed to enter into the London Highway Alliance Contract (LoHAC) for an eight year period commencing 1 April 2013. 2. LoHAC is a collaborative highways contract developed jointly by London boroughs and Transport for London (TfL). LoHAC is used by boroughs and TfL to carry out a wide range of tasks using the services of four area-based contractors. 3. The Royal Borough of Kingston is located within the South Area of LoHAC, where the partner contractor is EM (formerly Enterprise Mouchel). The geographic regions covered by the four areas are shown in Annex 1.
4. LoHAC is designed to allow councils to call-off the services of its choice from those available. As shown in Annex 2, Kingston is currently using fourteen of the available twenty-three services.
5. During the first year of implementation of LoHAC in Kingston, a robust and clearly defined approach to contract management, partnership and governance has been designed. This replicates similar contract arrangements operating within the Council and involves a clear structure of meetings with defined roles for each meeting.
Review of the year
6. It has been a productive first year of implementation through LoHAC. The approximate value of work undertaken through LoHAC during 2013/14 was £3.8m.
7. Each Neighbourhood Committee’s Planned Works Programmes and a number of reserve schemes have all been successfully completed, as have the Principal Road schemes largely funded by TfL. Reactive works have generally been completed in a timely manner and the highway maintained to a high standard.
8. Undertaking work through LoHAC required a new approach to contract management in RBK. This was due to the nature of the contract, which is New Engineering Contract, or NEC Engineering and Construction Contract (NEC3). The procedures in this contract style required the development and implementation of new procedures, which have been successfully implemented through the effort made by all staff involved.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Surbiton Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Appointment of Chair and Vice-ChairRESOLVED that: 1. Councillor Tom Reeve be appointed Chair of the Committee for the Municipal Year 2026/27 until the f...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.