Slip Road at 525 - 543 Hook Road -results of Safety Audit and consultations of TfL and Emergency Services
DecidedCommittee3 papers
the Borough Neighbourhood Committee decided this item on Wednesday 4 February 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED that 1. the proposal for the experimental closure of the slip road set out in Annex 1 is not introduced at this time; 2. a further safety audit is undertaken on an alternative layout, which replaces current signage with No Entry signs, and whereby the location shown hatched on the plan at ... view the full minutes text for item 82.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Version Status Date A Audit report issued to Client 27th January 2015 Hook Road / Bridge Road Roundabout Experimental Service Road Closure Combined Stage 1 & 2 Road Safety Audit Report
1.0INTRODUCTION 1.1 Commission 1.1.1 This report results from a Combined Stage 1 & 2 Road Safety Audit carried out on the proposals to close the Hook Road / Bridge Road roundabout service road to vehicular traffic for an experimental period. The Audit was undertaken by Capital Traffic in accordance with the Audit Brief confirmed by the Design Organisation on 14th January 2015. It took place at the Great Yeldham offices of Capital Traffic on 22nd January 2015 and comprised an examination of the documents provided as listed in Appendix A, plus a visit to the site of the proposed scheme. 1.1.2 The visit to the site of the proposed scheme was made on 22nd January 2015. During the site visit the weather was fine and the existing highway surfaces were dry.
1.2Terms of Reference 1.2.1 The Terms of Reference of this Audit are as described in TfL Procedure SQA-0170 dated May 2014. The Audit Team has examined and reported only on the road safety implications of the scheme as presented and how it impacts on all road users and has not examined or verified the compliance of the designs to any other criteria. However, to clearly explain a safety problem or the recommendation to resolve a problem the Audit Team may, on occasion, have referred to a design standard without touching on technical audit. An absence of comment relating to specific road users / modes in Section 3 of this report does not imply that they have not been considered; instead the Audit Team feels they are not adversely affected by the proposed changes. 1.2.2 This Safety Audit is not intended to identify pre-existing hazards which remain unchanged due to the proposals; hence they will not be raised in Section 3 of this report as they fall outside the remit of Road Safety Audit in general as specified in the procedure SQA-0170 dated May 2014. Safety issues identified during the Audit and site visit that are considered to be outside the Terms of Reference, but which the Audit Team wishes to draw to the attention of the Client Organisation, are set out in Section 4 of this report. 1.2.3 Nothing in this Audit should be regarded as a direct instruction to include or remove a measure from within the scheme. Responsibility for designing the scheme lies with the Designer and as such the Audit Team accepts no design responsibility for any changes made to the scheme as a result of this Audit. 1.2.4 In accordance with TfL Procedure SQA-0170 dated May 2014, this Audit has a maximum shelf life of 2 years. If the scheme does not progress to the next stage in its development within this period, then the scheme should be re-audited. 1.2.5 Unless general to the scheme, all comments and recommendations are referenced to the detailed design drawings and the locations have been indicated on the plan located in Appendix B. 1.2.6 It is the responsibility of the Design Organisation to complete the Designer’s response section of this Audit report. Where applicable and necessary it is the responsibility of the Client Organisation to complete the Client comment section of this Audit report. Signatures from both the Design Organisation and Client Organisation must be added within Section 5 of this Audit report. A copy of which must be returned to the Audit Team.
Audit Ref: 1187-RSA-01 Date: January 2015 2 Version: A Hook Road / Bridge Road Roundabout Experimental Service Road Closure Combined Stage 1 & 2 Road Safety Audit Report
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow the Borough Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.