Resolved
Resolved that the progress made in meeting the recommendations of the external auditors is noted.
Audit, Governance and Standards Committee noted this item on Thursday 16 April 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the progress made in meeting the recommendations of the external auditors is noted.
1. Note the progress made in meeting the recommendations set out by the Councils external auditors.
Key Points
A. A number of recommendations were made by our external auditors, Grant Thornton, as part of their external audit of the Councils Main and Pension Fund accounts. Progress made in meeting these recommendations is detailed below.
Context
1. The Audit Committee approved the Councils audited Main and Pension Fund accounts on 24 September 2014. As part of the audit process our external auditors, Grant Thornton, made a number of recommendations as part of their audit findings report. These are detailed below along with an update of how the Council has addressed the issue raised. Updates against progress were given at the previous January 2015 Audit Committee meeting.
2. The recommendations for the Councils Main accounts and progress made meeting the recommendations are as follows:
Recommendation 1 – Continue working towards the next phase of savings plans through ‘One Kingston Phase 2’ to deliver balanced budgets from 2015/16
With the announcement of the Provisional Local Government Finance Settlement in late December 2014, the 2015/6 budget has been balanced and was approved at the Strategic Committees in February and Full Council on 3 March 2015.
Savings plans have been adopted by the Strategic Leadership Team and Directorate Management Teams in conjunction with Portfolio holders through an iterative process during the autumn of 2014. These plans not only focus on 2015/16 but also on the medium term beyond that.
The Destination Kingston financial and service plan to Strategic Committees and Full Council will set out the medium term financial challenge. Detailed assumptions about the funding of Local Authorities and RBK in particular beyond 2015/16 have not been released, but the key messages from the Chancellor’s 2014 Autumn Statement indicate that resources will continue to decline for at least another parliamentary term.
The estimated budget gap existent beyond 2015/16 is:
Year Current Budget Gap £m 2015/16 0 2016/17 9.9 2017/18 16.5 2018/19 24.0
These figures were reported to Members in the Medium Term Financial Plan within the Destination Kingston papers to Strategic Committees and Full Council in February/March 2015.
Recommendation Status – In progress Risk rating - Amber
Recommendation 2 – Develop detailed plans with the London Borough of Richmond upon Thames and other partners to identify areas for shared services in order to deliver savings and maintain service delivery
The Thames Agreement programme with the London Borough of Richmond commenced in the Summer of 2014 and was tasked with looking at how services might be joined together to produce savings, innovation and resilience through this strategic collaboration. Exploratory work looked at the Target Operating Model; Strategic Services; Support Services; Health and Adult Services; Environment Services and Culture & Sport Services.
Proposals were presented to a Member Sponsor Board in Dec 2014 and it was agreed that for the time being that the Thames Agreement would be suspended and that the Councils would be free to explore other opportunities and partnerships.
This has allowed work on the transformation and re-commissioning programme to be accelerated. The programme is expected to be launched in Spring 2015, with early work being based around four themes:
• @Kingston – Kingston’s Identity • Growth • Helping People Prosper • Engagement and Capacity Building This programme will now be the main vehicle for delivering financial savings and making any changes to models of service delivery over the medium term.
Recommendation Status – In progress Risk rating - Amber
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2013/14 External Audit recommendations updateReport | 90 KB | DownloadRead as text |
Follow Audit, Governance and Standards Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Jan 2026 | 2024/25 External Audit of AccountsRESOLVED to amend the recommendations as follows: 4. Authority be given to the Chair of the Committee to sign the fin... | Agreed | Open |
| 25 Jun 2025 | MinutesRESOLVED that the minutes of the meeting held on 27 March 2025 be confirmed as a correct record. | Decided | Open |
| 27 Mar 2025 | MinutesRESOLVED that the minutes of the meeting held on 26 February 2025 are a correct record. | Decided | Open |
| 27 Mar 2025 | Internal Audit Charter and strategy, and internal audit plan 2025/26RESOLVED that that the Internal Audit Charter, Strategy and Internal Audit Plan for 2025 /26 be approved. Voting: Una... | Approved | Open |
| 26 Feb 2025 | MinutesRESOLVED that the minutes of the meeting held on 7 November 2024 are a correct record. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.