Resolved that 1. in response to the requirement for a local authority to have in place proper arrangements for the governance of its affairs and to undertake an annual open and honest assessment of its governance framework, it is noted that the Council has undertaken and agreed an assessment of its corporate governance arrangements; 2. the development of a programme of work to address the improvement areas set out in Table 1 (paragraph 11) is being developed is noted and that an Action Plan, along with the Annual Governance Statement, 2014/15 itself, will be brought back to the September meeting of the Committee for approval; 3. the report to the September meeting include additional information on contract management , the signing off of contracts and ensuring that they are signed and an appropriate representative either from the Council or the Shared Legal Service be requested to attend the September meeting to explain the position on signing of contracts and any contributory factors on unsigned contracts; 4. the latest position on the implementation of the 2014/15 AGS Action Plan as set out in paragraphs 19 and 20 is noted.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Report to Audit, Governance and Standards Committee
APPENDIX 1
2014-15 Annual Governance Statement Action Plan – Final Review June 2015
Ref Area Issue Action Current Status Owner Projected (June 2015) Complete Date
AGS1 Risk • The business continuity • External consultancy (AB) Updated Business AB July 2015 Management framework and service support engaged to Continuity Plan and Policy business continuity plans support review and update approved by SLT on 18 need updating. of RBK Business Continuity November. Individual Framework. This will Service Business include updated service Continuity Plans in process business continuity plans of being updated with for all areas of critical revised target of end of council activity. July 2015 for completion.
Consultation on risk Completed • Guidance on risk management with March • Improved guidance on escalation in RBK Risk members of all DMT’s 2015 risk escalation Management Toolkit to will be completed Jan procedures was be reviewed. 2015. Guidance on risk requested. escalation to form part of an updated Risk Management Toolkit with target date for escalation guidance of March 2015.
All existing Corporate Completed • All Corporate Risk Risk Action Plans have • Risk owners need to Action Plans to be been reviewed and ensure that risk action reviewed and updated updated as part of an plans are kept up to date where necessary. overall review of the and reviewed on a Corporate Risk regular basis. Registers by the Directorate Management Teams. All have confirmed as of Dec 2014 that this has been completed. Ref Area Issue Action Current Status Owner Projected (June 2015) Complete Date
AGS2 Performance Whilst services have • BK Data Quality (JRe) Data Quality JRe October Management effective arrangements Strategy to be reviewed Strategy is being 2015 in place for performance and updated. reviewed and is management some expected to be updated concerns were raised by March 15 about the perceived 06/2015 Review under absence of a corporate way. data quality strategy
AGS3 Financial • A new programme of (AR) (Staff Awareness AR Completed Management • Staff awareness of training to help staff of Financial End Jan financial with changes to Responsibilities) 2015 responsibilities could Agresso is due to begin During 2014-15 the new be improved in some in late summer and the Chart of Accounts areas. importance of managers within Agresso went taking responsibility for live. This has made the budgets and engaging coding structure more fully with budget logical and facilitates management will be improved provision of reinforced as part of the financial information. programme. The One Council Finance Toolkit is available on the intranet. The Toolkit includes, amongst other things, financial
regulations, budget manager responsibilities, links to Evolve modular online financial management training (A Year in the Life of a Budget manager). Uptake of the Evolve module is being monitored and Ref Area Issue Action Current Status Owner Projected (June 2015) Complete Date reported to Heads of Service so that they can ensure all budget managers complete it.
• Links between service (JRa)Work to get activity and financial managers to take full JRa Completed performance should be responsibility of their Early reinforced following budgets, and to 2015 review of chart of understand better the accounts and links between activity • Manager awareness of introduction of Ash and performance is links between service Debtors system. These ongoing. Bespoke activity data and actions will enable more training for managers financial performance effective extraction and was carried out jointly analysis of financial with Strategic Business data. took place during the first quarter of 2015.The Agresso AR (Ash debtors replacement) went live in March2015.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit, Governance and Standards Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
2024/25 External Audit of AccountsRESOLVED to amend the recommendations as follows: 4. Authority be given to the Chair of the Committee to sign the fin...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.