Resolved
Resolved that the work undertaken by Internal Audit, the Priority 1 issues raised and the implementation of the expansion of the shared service is noted.
Audit, Governance and Standards Committee noted this item on Wednesday 13 January 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the work undertaken by Internal Audit, the Priority 1 issues raised and the implementation of the expansion of the shared service is noted.
Audit, Governance and Standards Committee
13 January 2016
INTERNAL AUDIT UPDATE Report by Head of Internal Audit and Investigations
Purpose To provide the Committee with an update on the work carried out by Internal Audit since September 2015. To provide members with an update on the extension of the shared internal audit service
Recommendation To RESOLVE : a) That the Audit, Governance and Standards Committee note the work undertaken by Internal Audit and Priority 1 issues raised. b) That Committee note the update on the expansion of the shared service.
KEY POINTS
A. The Audit, Governance and Standards Committee has, amongst other things, responsibility for the “review of internal audit strategy, plans and performance; consideration of a summary of the most significant issues arising from internal audit work; and obtaining assurance that appropriate action is being taken on those issues.” This report has been provided to assist the Committee in meeting its responsibilities. B. It is considered that a quarterly update to the Committee on the work of Internal Audit is more helpful than ad-hoc reports to the Committee in meeting its responsibilities with respect to Internal Audit. C. The proposal to extend the shared service to include LB Sutton was approved by the Treasury Committee on the 3rd December 2015. PROGRESS AGAINST PLAN 2015/16 1. Progress against the 2015/16 plan as at 30th November 2015 is as follows:
Audits Days
Number of audits in the plan 48 687
Number of audits carried forward from 17 2014/15
Audit Days delivered 321
Audit management & advice to managers 31
Follow Up on Previous recommendations 12
Number of audits finalised* 22
Number of audits at draft report stage* 6
Number of audits in progress * 14
Number of audits booked to start 3
Number of audits cancelled 5 (* includes 2014/15 audits carried forward to this year’s plan)
2. The agreed deliverable audit days commissioned from the shared service was 800 days which included 657.5 days for RBK and 285 days for AfC, split equally between LBR and RBK (142.5 days each). The agreed audit plan included 679 days however, currently, as a result of additions, changes and work brought forward the plan now has 687 days, an excess of 29.5 days (against the 657.5). It is expected that these days will be reduced through a combination of in-year cancellations, audits being rolled forward to 2016/17 and also changes to agreed audit budgets to reflect changes to coverage for specific audits. 3. At the time of this report, approximately 55% of the plan has been completed on the basis of number of days delivered. This compares to 54% reported to Committee at the same time last year. This year’s plan is weighted towards the second half of the year with more audits being planned in Quarters 3 and 4 than in Quarters 1 and 2.
4. The total number of pieces of audit work completed or which are work in progress is 42. A further 3 pieces of work have been booked to start and 5 audits have been cancelled. It should be noted that there are currently 2 pieces of work from the 2014/15 plan that are at draft report stage. Internal Audit is working with management to get these reports finalised as quickly as possible. 5. Annex 1 details the 2015/16 Internal Audit Plan and shows the status of work to date with the assurance level for completed audits along with any audits that have been cancelled.
6. Internal audit visits Directorate Management Teams a number of times throughout the year to discuss progress against the plan and to review the audits which are still to be undertaken to ensure they are still relevant and timely.
REPORTS FINALISED SINCE THE LAST AUDIT COMMITTEE AND SIGNIFICANT CONTROL WEAKNESSES
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit: UpdateReport | 106 KB | DownloadRead as text |
Follow Audit, Governance and Standards Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Jan 2026 | 2024/25 External Audit of AccountsRESOLVED to amend the recommendations as follows: 4. Authority be given to the Chair of the Committee to sign the fin... | Agreed | Open |
| 25 Jun 2025 | MinutesRESOLVED that the minutes of the meeting held on 27 March 2025 be confirmed as a correct record. | Decided | Open |
| 27 Mar 2025 | MinutesRESOLVED that the minutes of the meeting held on 26 February 2025 are a correct record. | Decided | Open |
| 27 Mar 2025 | Internal Audit Charter and strategy, and internal audit plan 2025/26RESOLVED that that the Internal Audit Charter, Strategy and Internal Audit Plan for 2025 /26 be approved. Voting: Una... | Approved | Open |
| 26 Feb 2025 | MinutesRESOLVED that the minutes of the meeting held on 7 November 2024 are a correct record. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.