Resolved
Resolved that t he report is noted and the actions taken by management and Internal Audit are endorsed .
Audit, Governance and Standards Committee noted this item on Wednesday 20 April 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that t he report is noted and the actions taken by management and Internal Audit are endorsed .
1. As part of the Audit Plan in 2015/16 Internal Audit has carried out follow–up work on previous audits where Priority 1 recommendations have been made. Reports have been presented to the Strategic Leadership Team (SLT) for consideration.
2. There are currently 13 Priority 1 recommendations outstanding, 12 of which are classified as Amber and 1 classified as Red. 3 further recommendations are classified as White There has been progress in completing recommendations since the previous report. Since we reported to Committee in February; 8 recommendations have been completed, a further 5 are substantially complete and 2 have been superseded as a result of a full review being planned in the forthcoming year.
3. Annex 1 provides details of the progress on the implementation of the Priority 1 recommendations which are currently outstanding i.e. Red or Amber RAG Status.
4. The following definitions are applied:
RAG Status
Not implemented (Red)
Implementation nearing completion or work plan in place (Amber) Implemented (Green)
Superseded, risk accepted by management or recommendation no longer relevant (White) Consultation
5. Individual audit reports are discussed and agreed with the appropriate officers and reports with high priority recommendations are presented to Heads of Service and Directors. SLT review the status of the report prior to presentation at audit committee.
Resource Implications 6. None arising directly from this report’s recommendations. All costs of the service will be met from within existing budget resources for the shared service.
Background papers – held by the Author of this report:
Alix Wilson – Head of the South West London Audit Partnership (SWLAP) Tel: 020 8547 4624, e-mail: [email protected] Annex 1 Priority 1 Recommendations Outstanding
Recommendation Original RAG Responsible Management Update Follow up/ Audit Date of Target Status Officer and comments next Date Director review Disaster Recovery (IT Audits) Management should Quarter 3 White Carl Progress has been made on providing DR A full DR audit N/A perform testing of the 2013/14 Godbehere / testing as applications and systems migrate into will be completed existing system recovery Leigh the new infrastructure. The power down of the in 2016/17. No procedures to determine Whitehouse Kingston data centre over the weekend 13/14 further follow up their adequacy and the Feb proved our capability to allow users of work to be level of assurance that systems to continue working while their data undertaken. can be placed on them. centre is unavailable. IAS was flipped to the Sutton data centre and remained available Furthermore, throughout the power down at Kingston. The Management should put need to traditional DR testing, while relevant for in place a procedure to some systems has, in some systems, become conduct annual testing of redundant. the Council’s formally defined Disaster Recovery plan once completed. Pensions Administration 1) The backlog of joiners 30 White Sue Progress has been made with entering new The backlog of N/A to be entered on Axis September Grimstead / starters on the system. new joiners has should be cleared in a 2013 Leigh reduced. timely manner. Whitehouse Backlogs exist on other work however and a 2) Statutory Notices full audit of giving details of Pensions Admin membership of the Local will be carried out Government Pension in 2016/17 jointly Scheme should be sent Annex 1 Priority 1 Recommendations Outstanding to all joiners of the with the London pension scheme within Borough of the time limit specified by Sutton. pension’s legislation. (Complete)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Recommendations: Follow upReport | 120 KB | DownloadRead as text |
Follow Audit, Governance and Standards Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Jan 2026 | 2024/25 External Audit of AccountsRESOLVED to amend the recommendations as follows: 4. Authority be given to the Chair of the Committee to sign the fin... | Agreed | Open |
| 25 Jun 2025 | MinutesRESOLVED that the minutes of the meeting held on 27 March 2025 be confirmed as a correct record. | Decided | Open |
| 27 Mar 2025 | MinutesRESOLVED that the minutes of the meeting held on 26 February 2025 are a correct record. | Decided | Open |
| 27 Mar 2025 | Internal Audit Charter and strategy, and internal audit plan 2025/26RESOLVED that that the Internal Audit Charter, Strategy and Internal Audit Plan for 2025 /26 be approved. Voting: Una... | Approved | Open |
| 26 Feb 2025 | MinutesRESOLVED that the minutes of the meeting held on 7 November 2024 are a correct record. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.