CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Royal Borough of Kingston upon Thames
Growth Committee, Tuesday 7 February 2017 at 7.30pm

Co-location of Job Centre Plus in Guildhall 2

Agreed Committee 2 papers

Growth Committee agreed this item on Tuesday 7 February 2017. Below is the council's own wording, with the papers it was decided on.

Item45

Resolved

It was agreed that the draft terms, as set out in Annex 2, should be exempt from publication by virtue of paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972. Resolved that 1. authority is delegated to the Director of Finance, in consultation with the Director of Place, to finalise and complete the leasehold disposal of part of the ground floor of the Guildhall 2 premises, to Job Centre Plus for a period of five years; and 2. the associated proposals to remodel floors two and three of the Guildhall 2 building to facilitate the co-location of Job Centre Plus on the ground floor are approved. Voting: Unanimous.
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Growth Committee

Growth Committee 7 February 2017

Co-location of Job Centre Plus in Guildhall 2 Report by the Director of Finance

Purpose

To approve the proposed co-location of Job Centre Plus in the ground floor of the Guildhall 2 building, and to approve the associated re-modelling of floors two and three of the Guildhall 2 building to accommodate this.

Recommendations of the Portfolio Holder for Regeneration To ​resolve​ that: 1. delegated authority is granted to the Director of Finance, in consultation with the Director of Place, to finalise and complete the leasehold disposal of part of the ground floor of the Guildhall 2 premises, to Job Centre Plus for a period of five years; and 2. to approve the associated proposals to remodel floors two and three of the Guildhall 2 building to facilitate the co-location of Job Centre Plus on the ground floor.

Key Points

A. The lease on Job Centre Plus’ (JCP) current accommodation in Kingston is due to expire in April 2018 and cannot be renewed. JCP are currently unable to find any suitable alternative accommodation within the borough. B. In view of this, JCP has been in discussions with the Council about the possibility of leasing accommodation from within the Council’s property portfolio. JCP’s requirements are for between 8,000 and 10,000 square feet of accommodation, in a town centre location, for a minimum period of five years. The only property within the Council’s portfolio that is capable of meeting these requirements is the Guildhall 2 building. C. Accordingly, it is proposed that JCP will be co-located with the Council’s Information and Advice Centre (IAC) in the ground floor of Guildhall 2 for a period of five years. D. A feasibility study has been undertaken which demonstrates that the proposed co-location can be achieved, although this is dependent upon the re-modelling of floors two and three of Guildhall 2 so that staff currently accommodated on the ground floor can be re-located. A draft floor plan which shows the co-location proposals for the ground floor, as well as the remodelling proposals for the second and third floors, is attached as Annex 1. E. Significant strategic and operational benefits are expected to flow from co-locating JCP with the Council’s IAC. These include an improved central point of access to a wider range of public services for local residents; the creation of a platform to facilitate innovation and integration between the services offered by the Department for Work and Pensions (DWP) and those offered by the Council; and the opportunity to modernise the main customer facing services operated by the Council.

F. Similarly, significant financial benefits are expected to flow from the associated leasehold disposal. These are yet to be agreed between the parties but are set out in draft at Annex 2. This information is considered commercially sensitive and so Annex 2 is included in the exempt part of this agenda.

G. The proposed co-location and the associated re-modelling works will create disruption for staff and customers on site for a period of up to 12 months. The feasibility work undertaken so far indicates that this can be mitigated by temporarily decanting staff into alternative locations. The feasibility study also indicates that the IAC can remain open throughout the works period.

H. The proposals, including the associated costs / contributions, are also subject to formal agreement by Job Centre Plus / the Department for Work and Pensions. A final business case is due to be considered by them in late January / early February.

Proposal 1. The proposed co-location of JCP in Guildhall 2 would require the sharing of the Ground Floor of the building. The consequential space impacts would result in knock on implications for teams based elsewhere in Guildhall 2. It is more appropriate therefore to see the proposal as one to remodel and repurpose Guildhall 2 for the Medium Term. This key elements of this are set out in the table below:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Co-location of Job Centre Plus in Guildhall 2Report 107 KB DownloadRead as text
PDF
Job Centre Plus (Annex 1)Appendix 3.7 MB Download

At this meeting

Whole meeting

Who was there

12 of 14 attended
BB
Councillor Bill BrisbaneMember, present
AC
Councillor Andrea CraigVice-Chair, expected
DC
Councillor David CunninghamChair, present
KD
Councillor Kevin DavisMember, present
SG
Councillor Sheila GriffinMember, present
JM
Jane MarwoodCo-Optee, expected
RP
Councillor Raju PandyaMember, present
PP
Councillor Priyen PatelMember, apologies, sent representative
CR
Councillor Cathy RobertsMember, present
MS
Councillor Malcolm SelfMember, present
KS
Councillor Ken SmithMember, present
TT
Councillor Thay ThayalanMember, present

All 14 on the meeting page

More from Kingston upon Thames Growth Committee

All decisions
MeetingDecisionOutcome
27 Mar 2018 Cultural StrategyResolved that: 1. ‘Made in Kingston: a creative and cultural strategy’, as set out in Annex 1, be adopted, setting th... Approved Open
27 Mar 2018 Buildings of Townscape Merit and Local Areas of Special CharacterResolved that: 1. the ‘Buildings of Townscape Merit’ designation is replaced by ‘Locally Listed Buildings’ as set out... Approved Open
27 Mar 2018 Tolworth Apple StoreResolved that the Head of Property be authorised to facilitate meetings and discussions between the Petitioners and t... Decided Open
27 Mar 2018 Appropriation for planning purposes of Neville House Yard Car ParkResolved that the Committee recommends that Council agrees to: 1. Appropriate for planning purposes Neville House Yar... Agreed Open
27 Mar 2018 Disposal of Neville House Yard Car ParkResolved that the Head of Property be granted delegated authority to proceed to dispose of the property, as shown on ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies