Resolved
RESOLVED that: 1. The update on the water fountain project is noted; 2. The sum of £18,936, comprising the Grove Ward Councillors’ 2016/17 Funding and underspends on discretionary funds are carried forward into an earmarked reserve pending future agreement on the project and the agreement of Treasury Committee in June 2017 concerning any underspend arrangements; 3. The Committee identifies suitable sources of additional capital funding of the order of £11,000; 4. The Committee identifies suitable sources of revenue funding to cover the estimated annual maintenance costs of £6,000; and 5. In the event that the project does not proceed and provided the carry forward is agreed, the Grove Ward Councillors will re-allocate their Ward councillor funding (£6K) and the committee re-allocates the remaining fund of £12,936. Voting: unanimously in favour