CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Royal Borough of Kingston upon Thames
Growth Committee, Tuesday 27 June 2017 at 7.30pm

Eden Walk Regeneration - In principle use of compulsory purchase powers

Agreed Committee 2 papers

Growth Committee agreed this item on Tuesday 27 June 2017. Below is the council's own wording, with the papers it was decided on.

Item71

Resolved

Resolved that the Committee: 1) recommends that Council agrees in principle to use compulsory purchase powers to acquire the land and new rights within the area described in the report and shown edged red on the plan attached to the report. The Council being of the view that compulsory acquisition of the land may be necessary in order to achieve the following: a) Secure the delivery of the Kingston Town Centre regeneration scheme and its housing, job-creation and transformational objectives; b) Facilitate the carrying out of the development by way of an agreed programme and timescale in partnership with the developer; and c) Contribute to the promotion and improvement of the economic, social and environmental well-being of the Borough. 2) recommends that Council delegates authority to the Growth Committee to make compulsory purchase orders arising out of the 'in principle' decision. 3) authorises Officers to begin preparatory work to use its compulsory purchase powers, including subject to the 'in-principle' decision being made, serving requisitions on land owners and appointing land referencing agents to thoroughly investigate all land interests, the preparation of a Statement of Reasons and all other necessary documentation. 4) notes that all necessary expenditure associated with such preparatory work (including legal fees, consultants’ fees, and any other investigation work or research) as well as any compensation payable to owners as a result of a future compulsory purchase order will be met in full by the developer and approve the entering of an indemnity agreement with the developer to secure this. 5) notes that, subject to consideration by Council, a further report will come forward to the Committee recommending the making of a compulsory purchase order, if necessary, in relation to specific land.
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Growth Committee

Growth Committee 27 June 2017

Eden Walk Regeneration – In Principle Use of Compulsory Purchase Powers Report by the Director of Place

Call-in deadline 5pm on 11 July 2017

Purpose

To pass a resolution recommending that the Council agrees, in principle, to use its compulsory purchase powers for the acquisition of land necessary for the delivery of the Kingston Town Centre regeneration scheme.

Recommendations of the Portfolio Holder for Regeneration

The Committee resolves -

1. To recommend that Council agrees in principle to use compulsory purchase powers to acquire the land and new rights within the area described in the report and shown edged red on the plan attached to this report. The Council being of the view that compulsory acquisition of the land may be necessary in order to achieve the following:

a) Secure the delivery of the Kingston Town Centre regeneration scheme and its housing, job-creation and transformational objectives;

b) Facilitate the carrying out of the development by way of an agreed programme and timescale in partnership with the developer; and

c) Contribute to the promotion and improvement of the economic, social and environmental well-being of the Borough.

2. To recommend that Council delegates authority to the Growth Committee to make compulsory purchase orders arising out of the 'in principle' decision.

3. To authorise Officers to begin preparatory work to use its compulsory purchase powers, including subject to the 'in-principle' decision being made, serving requisitions on land owners and appointing land referencing agents to thoroughly investigate all land interests, the preparation of a Statement of Reasons and all other necessary documentation.

4. To note all necessary expenditure associated with such preparatory work (including legal fees, consultants’ fees, and any other investigation work or research) as well as any compensation payable to owners as a result of a future compulsory purchase order will be met in full by the developer and approve the entering of an indemnity agreement with the developer to secure this.

5. To note that, subject to consideration by Council, a further report will come forward to Committee recommending the making of a compulsory purchase order, if necessary, in relation to specific land. Key Points

A. The regeneration of the part of Kingston Town Centre area known as Eden Walk was granted planning permission on 8 December 2016 (Eden Walk). A further planning application to develop Gough House, also within the Town Centre area, has been made to the Council and is due for determination in July/August 2017 (Gough House). The regeneration of Kingston Town Centre via the redevelopments of Eden Walk and Gough House in this report is together known as the Scheme.

B. The Eden Walk part of the Scheme will be developed by the Universities Superannuation Scheme and British Land (together the Developer). The redevelopment of Gough House will be carried out by another developer in collaboration with the Developer and as part of the Scheme.

C. The Council supports the Scheme and wishes bring forward the regeneration to Kingston Town centre as soon as possible. The Scheme is considered to bring significant housing, jobs and economic investment in Kingston.

D. It is envisaged that use of the Council's powers to acquire land by a compulsory purchase order (CPO) may be required in order to assemble all of the land interests and rights required to develop the Scheme in a timely manner. Therefore the Director of Place seeks authority to begin preparatory and planning work to use its CPO powers for all the land interests not yet in the ownership or control of the Developer needed to facilitate the Scheme.

E. Subject to agreement by Council, it should be noted that all requests to pass a resolution to make and serve CPO's will be made in separate future decision(s) by the Growth Committee only once the following conditions have been reached, namely:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(CPO Plan)Appendix 1 1.1 MB Download
PDF
Eden Walk Regeneration: In principle use of compulsory purchase powersReport 133 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 14 attended
PB
Councillor Patricia BamfordMember, present
BB
Councillor Bill BrisbaneMember, present
DC
Councillor David CunninghamChair, present
KD
Councillor Kevin DavisMember, present
SG
Councillor Sheila GriffinMember, apologies, sent representative
CH
Councillor Chris HayesMember, present
AJ
Councillor Andy Johnson-CreekVice-Chair, present
JM
Jane MarwoodCo-Optee, present
RP
Councillor Raju PandyaMember, apologies, sent representative
CR
Councillor Cathy RobertsMember, present
MS
Councillor Malcolm SelfMember, present
KS
Councillor Ken SmithMember, present

All 14 on the meeting page

On this subject at Kingston upon Thames

Search all
  1. Eden Walk Regeneration - In principle use of compulsory purchase powersThis decision
  2. Eden Walk Regeneration - Use of Compulsory Purchase PowersAgreed
  3. (b) Eden Walk Regeneration - in principle use of compulsory purchase powersAgreed

More from Kingston upon Thames Growth Committee

All decisions
MeetingDecisionOutcome
27 Mar 2018 Cultural StrategyResolved that: 1. ‘Made in Kingston: a creative and cultural strategy’, as set out in Annex 1, be adopted, setting th... Approved Open
27 Mar 2018 Buildings of Townscape Merit and Local Areas of Special CharacterResolved that: 1. the ‘Buildings of Townscape Merit’ designation is replaced by ‘Locally Listed Buildings’ as set out... Approved Open
27 Mar 2018 Tolworth Apple StoreResolved that the Head of Property be authorised to facilitate meetings and discussions between the Petitioners and t... Decided Open
27 Mar 2018 Appropriation for planning purposes of Neville House Yard Car ParkResolved that the Committee recommends that Council agrees to: 1. Appropriate for planning purposes Neville House Yar... Agreed Open
27 Mar 2018 Disposal of Neville House Yard Car ParkResolved that the Head of Property be granted delegated authority to proceed to dispose of the property, as shown on ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies