Jubilee Way Cycle Scheme

Noted Committee 1 paper

the Borough Neighbourhood Committee noted this item on Wednesday 24 January 2018. Below is the council's own wording, with the papers it was decided on.

Item40

Resolved

To Resolve that – 1. the recommendations of the ecological survey, as set out in paragraphs 7-13 of the report, are noted. 2. the scheme now proceeds to detailed design and implementation, subject to recommendations of the ecological survey as set out in the report; and 3. the Team Leader Strategy and Commissioning is authorised, in consultation with the Ward councillors, to finalise the design of the scheme for implementation.
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to the Borough Neighbourhood Committee

South of the Borough Neighbourhood Committee 24 January 2018 Jubilee Way Cycle Scheme Report by the Interim Head of Shared Environment Services

Call-in deadline 5pm Wednesday 7 February 2018 (ten working days after the meeting)

Purpose To consider the findings and recommendations of the ecological survey undertaken to assess the potential impacts of the proposed cycle scheme, on the southern section of Jubilee Way.

Recommendations To ​Resolve​ that - 1. the recommendations of the ecological survey, as set out in paragraphs 7-13 of the report, are noted. 2. the scheme now proceeds to detailed design and implementation, subject to recommendations of the ecological survey as set out in the report; and 3. the Team Leader Strategy and Commissioning is authorised, in consultation with the Ward councillors, to finalise the design of the scheme for implementation.

Key Points A. In December 2015 this Committee considered a report on proposals to introduce a cycle scheme on the southern section of Jubilee Way, from the boundary with Cox Lane as far up as the K2 bus stops outside the King George playing Fields. At that time the scheme was approved, subject to the outcomes of an ecological survey on the area of vegetation along the eastern side of the road. Unfortunately, it has taken some long time for this report to be completed, and for officers to report back on those findings. B. The Biodiversity Network indicated that the area of proposed vegetation clearance for the cycle route is in the vicinity of Tolworth Court Farm Local Nature Reserve for which the statutory protection may extend to the road edge. Tolworth is a stronghold for two reptile species protected by legislation (slow worms and common lizard) and it was indicated that full ecological surveys would be required to ensure the loss to biodiversity is suitably quantified and mitigated. Reptile surveys had to be timed and spaced according to Best Practice Guidelines. In the event, no Grassland Reptiles were recorded during the surveys and there is no requirement for any further surveys. C. The other recommendations of the ecological survey relating to bats, badgers and birds are set out in paragraphs 7 -12 of the report. D. At the time of that report there was also an outstanding design that was put on hold, which related to the layout of the Cox Lane/Jubilee way section of road, where cyclists would be expected to join the shared facility on the east side. This design feature will be resolved and addressed as part of the detailed design for the scheme in discussion with Ward councillors and Kingston Cycle Campaign and other interested parties. A formal pedestrian point of access into the Tolworth Court Farm area will also be considered as part of the detailed design discussions. Context

1. The report on the ecological surveys identified a range of mitigation measures to avoid direct impacts to species of principal importance, features with potential to support roosting bats, as well as maintain the ecological functionality of the site as a commuting and foraging resource for bats are provided below. The report covered the impacts on birds, bats, badgers and reptiles. 2. It is considered timely that this matter should be brought back to the Committee to progress, as the recent Planning Approval for the LIDL Headquarters on the south-west corner of Jubilee Way/A240 Kingston Road will see significant development of that site, which will itself involve improvements to the footways and cycle facilities in and around the junction. 3. It is also noted that as part of the Planning Permission for the recently completed Premier Inn site, a contribution of £75,000 was secured towards further works on improvements to the pedestrian and cycle facilities along the remaining section of Jubilee Way, i.e. between the proposals at the southern end and the development site at the northern end.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Jubilee Way Cycle SchemeReport 80 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
SJ
Simon JakemanCommunity Representative, present
RR
Councillor Rachel ReidChair, present
AD
Councillor Andrew DayMember, present
MT
Councillor Margaret ThompsonMember, present
PB
Councillor Patricia BamfordMember, apologies
SM
Councillor Shiraz MirzaMember, apologies
CC
Councillor Clive ChaseMember, present
LD
Councillor Lorraine DunstoneVice-Chair, present
TT
Councillor Thay ThayalanMember, present
TD
Councillor Tom DaviesMember, apologies
ST
Sue TownerCommunity Representative, present

On this subject at Kingston upon Thames

Search all
  1. Jubilee Way Cycle SchemeThis decision
  2. Jubilee Way Safer Crossing Point and Cycling FacilityDecided
  3. Jubilee Way Cycling and Walking LinkDecided
  4. Site at Jubilee WayApproved
  5. Lease of Car Park Site at Jubilee Way/Cox Lane, ChessingtonAgreed
  6. Lease of Car Park Site at Jubilee Way/Cox Lane, ChessingtonAgreed

More from Kingston upon Thames the Borough Neighbourhood Committee

All decisions
MeetingDecisionOutcome
10 Sep 2026 Community grant applicationsRESOLVED that: 1. the application for a £3,000 Neighbourhood Community Grant from Voices of Hope, as set out in parag... Approved Open
11 Jun 2026 Appointment of Chair and Vice-Chair for 2026/27 Municipal YearIt was RESOLVED that; 1. Councillor Lorraine Dunstone be appointed Chair of the Committee for the Municipal Year 2026... Decided Open
11 Jun 2026 Objections to double yellow lines- Compton Crescent, Marston Avenue, Elmcroft Drive, Bridge Road junction with Leatherhead road, KnollmeadScheme 1. Elmcroft Drive RESOLVED that – 1 the comments and objections received as set out in paragraphs 2 and 7 and ... Noted Open
11 Jun 2026 Community Grant ApplicationRESOLVE D that – 1. the application for a Neighbourhood Community Grant of £3,000 from New Era Community Projects CIC... Approved Open
11 Jun 2026 Neighbourhood Working Arrangements 2026 - 2030RESOLVED that – 1. Planning Sub-Committee not be established for the 2026-30 municipal term; and 2. that a ‘guillotin... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies