RESOLVED that – 1) the current agency contract with Adecco be extended by means of variation, for a period of twelve months to April 2020; and 2) the Director, Corporate and Commercial be authorised to put in place a deed of variation to allow a contract variation term of 12 months.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Finance and Contracts Committee 18 March 2019 Recruitment Agency Contract Director, Corporate & Commercial
Purpose
To approve a variation to the existing agency recruitment contract with Adecco for a period of twelve months until April 2020.
Recommendations - 1) the current agency contract with Adecco be extended by means of variation, for a period of twelve months to April 2020; and 2) the Director, Corporate and Commercial be authorised to put in place a deed of variation to allow a contract variation term of 12 months.
Benefits to the Community The contract provides SME businesses an opportunity to supply their services to local authorities, while being commercially competitive in ensuring best value for the Council. 80% of the Adecco supply chain are SME businesses, which provides local workers with employment and training opportunities. We ensure expeditious payment to Adecco, which in turn ensures they can pay their supply chain promptly, which importantly helps the SME business cash flow.
Key Points
A. The Council’s contract for agency workers is currently delivered by Adecco. Achieving for Children also procure their agency workers by means of a contract addendum through this contract. This contract excludes any agency workers who are supplied through Executive Search agencies. B. The existing framework under which the contract is delivered is due to expire. Officers have evaluated that further time is needed to appraise the various commissioning options for how the Council secures its agency and professional services. C. It has also transpired that potential procurement routes that were expected to be active in preparation for the end of the original Adecco contract are not in place until October 2019 at the earliest and so further time is needed to ensure the Council has all options open to it. For these reasons, a variation of time on the original contract is recommended to ensure that BAU processes can continue and the Council has access to agency staff provision whilst it carries out its commissioning activity. As a result there is now a requirement to vary the end of the contract period from 18th April 2019 until 17th April 2020. D. This will provide the Council with continuity of service with the current providers (Adecco) while longer-term arrangements for the sourcing of agency workers are fully explored. The current contract offers the Council the greatest benefits commercially without any impact on services, internal clients or the wider market. E. HR are also undertaking an internal review and the route through which agency workers are engaged and the process in how the service is delivered is likely to change during the period of the variation term. Conversations with various stakeholders are underway to consider options for a new model and way of working.
F. The variation is currently going through the formal sign off process in accordance with the Council’s Contract Standing Orders and a verbal update will be given at Finance and Contracts Committee.
Context
1. The variation value is approximately three and a half million pounds with a variation term of 12 months. Contracting with Adecco in this way has delivered year-on-year efficiency and financial savings to the council.
2. Over the last 6 months, Officers have led a wide-ranging programme of work to review and reduce the council’s use of agency workers. This had led to a significant reduction in the number of agency workers engaged at the Council.
Proposal and Options
3. The recommended option to vary the contract with Adecco provides the best commercial arrangements for the Council. This option delivers the financial benefit while also providing the service delivery and non-financial benefits available from the alternative options. In addition, the time and cost of transitioning to an alternative arrangement for a relatively short time frame are prohibitive.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Finance and Renegeration Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.