Resolved to Permit subject to the conditions and informatives as set out in the agenda report and associated late material, additional conditions as set out below and the completion of relevant legal agreements under the Town and Country Planning Act 1990 (as amended), as specified in the legal agreements section, and to delegate to the Head of Development Management (Acting) any consequent changes to conditions and legal Page A51 A51 agreements to be agreed in consultation with the Chair of the Planning Committee: · On Street accessible parking bays be dealt with by way of the legal agreement - To amend the legal agreement section to Include provision of two onstreet offsite disabled parking bays/ accessible spaces without prejudicing existing disabled parking in Kingston. Voting: For: Councillors Self, Bailey, Beynon, Dunstone , Ryder-Mills, Heap, Arora, Cunningham (8) Against: Councillor Wehring (1) Abstentions: Councillor Edwards 21/01951/FUL - 187 Ewell Road, Surbiton, KT6 6AP This application had been withdrawn prior to the commencement of the meeting.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
21/02313/FUL - Greencoat House 165-183 Clarence Street Kingston Upon Thames KT1 1QT
Finished Floor Levels & Means of Escape
1. Following the publication of the Planning Committee Agenda the applicant has submitted the following additional information:
● Technical Note - 7591/01 - FRA Addendum ● GH-PL0130, Rev A, Proposed Cross Section AA, dated 07.01.2022 ● GH-PL0111, Rev A, Proposed GA plan - Level 0 Ground Floor, dated 07.01.2022
2. The submitted information confirms that the Finished Floor Level (FFL) will be 8.91mAOD which means that there would be a 630mm freeboard above the flood level for the site, and 600mm above the flood level provided by the two closest nodes to the development site.
3. The Technical Note confirms that there is a safe dry evacuation route from the site in a flood event southwards along Clarence Street, eastwards along Fairfield North and southwards to Fairfield East which is located within Flood Zone 1.
4. In light of the above, Officers are satisfied that the issues raised in paragraphs 57 - 61 of the Committee Report have been addressed, subject to an additional planning condition requiring full details of the raised FFL and access arrangements prior to the beneficial occupation of any of the Large-Scale Purpose-Built Shared Living accommodation.
Additional Condition
Details of the ground floor Finished Floor Levels and level access arrangements shall be submitted to the local planning authority prior to commencement of above ground works. The approved details shall be implemented prior to the beneficial occupation of any of the Large-Scale Purpose-Built Shared Living accommodation. Reason: To ensure level access and an appropriate level in relation to any flooding event pursuant to Policy DM4 of Kingston’s Core Strategy (2012) and D5 (Inclusive Design) and SI 12 (Flood Risk Management) of London Plan (2021).
Operational Management Plan
5. The applicant has submitted an amended Operational Management Plan (OMP), Version 2, which has sought to provide additional details in line with paragraph 4.16.4 of Policy H16 of the London Plan (2021). The revised OMP alludes to a Fire Management Plan being put in place to ensure that the scheme and operations conform with fire regulations and that tenants will be made aware of the fire safety and that on-site management staff will be trained on fire alarm procedures and processes in the event of a fire. The proposed approach is welcomed, however, it is considered necessary to require an updated OMP prior to the beneficial occupation of the development hereby approved to ensure that the final OMP required by Policy H16 of the London Plan (2021) is sufficiently detailed.
Additional Planning Condition:
Prior to the beneficial occupation of the large-scale purpose-built shared living accommodation hereby approved, an updated Operational Management Plan which fully addresses the detailed requirements set out under Policy H16 of the London Plan (2021) shall be submitted to the Local Planning Authority for approval in writing. The development shall thereafter be carried out in accordance with the approved Operational Management Plan, unless otherwise first agreed in writing by the Local Planning Authority.
Reason: To ensure that the proposed accommodation is of a continued good standard in accordance with Policy H16 of the London Plan (2021).
Planning Contribution
6. The applicant has confirmed that they would be willing to contribute £50,000 towards Public Realm & Urban Greening improvements within the vicinity of the site.
Additional Representations Received
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.