Resolved to Refuse the application on grounds 1, 2 and 3 as detailed in the Agenda report 1. Impact on amenities of surrounding occupiers 2. Scale, mass and design 3. Affordable housing (and legal agreement for other matters) Voting: For: Councillors Bailey, Heap, Cunningham, Wehring and Ryder-Mills (5) Against: Councillor Self, Edwards and Arora (3) Abstain: Councillor Archer (1) Item A3 - 21/03311/KPSI - King Charles Centre, Hollyfield Road, Surbiton, KT5 9AL Description: Demolition of existing building and construction of new part-one, part three storey primary school along with associated parking, hard and soft play areas. The Committee agreed to take Item A3 ahead of Item A2 as the item had registered speakers. Public Speakers: For - Applicant Against Nicholas Taylor [name removed] Croft Duncan Purvis Stefan Harris Matthew Paul Councillors who addressed the Committee under Part B - Paragraph 6.2 (6) of the Council’s Planning Protocol (in support of an application) Councillor Sushila Abraham Resolved to Permit subject to the condition(s) and informatives as set out in the agenda report and the amended and additional conditions as set out in the published late material, and additional conditions set out below; A requirement in the Legal Agreement for the Applicant to work with the highways authority to explore measures and funding streams for the introduction of a safe environment, which could include, but not be limited to School Street, crossing, zig zags. The solution to be drawn up in ... view the full minutes text for item 19.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
1. Email from applicant confirming 55 FTE staff with the total number of junior school staff being 99.
2. Updated drawings received from applicant on 08.02.22 to ensure consistency of drawings:
● Site and drawing reference plan - 4155-BBLA-ZZ-ZZ-DR-L-001-P3 ● Landscape general arrangement plan 3 of 4 - 4155-BBLA-ZZ-ZZ-DR-L-103-P3
3. Late response received from Metropolitan Police (07.02.2022) raising no objections subject to conditions.
[RBK Officer Comment: new conditions are set out below]
4. Late response received from Transport for London (27.01.2022):
The site is less than 310 metres from the A3 Kingston Bypass, which forms part of the Transport for London Road Network (TLRN). TfL is the highway authority for the TLRN, and is therefore concerned about any proposal which may affect the performance and/or safety of the TLRN.
A total of 64 car parking spaces are proposed. Although there are no specific restrictions on car parking for schools in the London Plan, the use of sustainable and active travel to support the objectives of the Mayor’s Transport Strategy and the London Plan should still be encouraged and it is considered that parking should be limited to staff members.
Electric Vehicle (EV) charging infrastructure (6 spaces) welcomed.
Cycle parking is in accordance with Policy T5 of the London Plan. These
1 should all be located in a secure, sheltered and accessible location and should meet London Cycle Design Standards (LCDS). At least 5% should be for larger and adapted cycles.
Service access and arrangements supported.
General support for construction programme details with the following needing to be addressed/secured:
● The use of a delivery booking system is supported and should be used to schedule all deliveries outside the network peak hours of 08:00-10:00 and 16:00-18:00. ● It is supported that operators will be required to be members of the Fleet Operators Recognition Scheme (FORS) and that Construction Logistics and Community Safety (CLOCS) standards will be enforced. ● It is supported that a full Construction Logistics Plan will be submitted and secured by condition. ● The footway and carriageway on the A3 Kingston Bypass must not be blocked during the development works. Temporary obstructions during the development works must be kept to a minimum and should not encroach on the clear space needed to provide safe passage for pedestrians or obstruct the flow of traffic on the A3 Kingston Bypass. ● All vehicles associated with the development must only park/ stop at permitted locations and within the time periods permitted by existing on-street restrictions. ● No skips or construction materials shall be kept on the footway or carriageway on the TLRN at any time.
General support for Interim School Travel Plan (STP) with the following needing to be addressed/ secured:
● Subsequent travel surveys to monitor the STP should be undertaken 3 and 5 years after the baseline survey. ● The STP should include measures for how sustainable and active travel will be promoted and how car-use will be reduced. This includes the incorporation of campaigns and events such as cycle or walk to school week. ● TfL requests that there is a commitment from the applicant to provide funding streams for the monitoring and management of the STP and that the STP is secured through a S106 agreement.
2 [RBK Officer Comment : These matters can be adequately addressed through conditions set out in the committee report, notably Condition 7]
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.