RESOLVED that: 1. As part of the Transform Kingston Programme, the Council commits to the provision of a new community leisure centre in Kingston Town Centre subject to planning permission and subject to the financing being confirmed at budget Council on 1 March 2022 2. It be noted that the facilities mix for the Town Centre, as set out in section 7 of the report, is aligned to the need and latent demand identified in the draft Indoor Leisure Facilities Strategy 2022. Voting: For: Councillors Archer, Moll, Davey, Heap, Kirsch, Thayalan, Wehring, Yoganathan. (8) Against: None. (0) Abstain: Councillors Arora, Cunningham, Hughes, Tolley. (4)
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
To provide a commitment to the new Community Leisure Centre in Kingston Town Centre replacing the Kingfisher Leisure Centre to be delivered within the Transform Kingston Programme. Additionally to provide an outline of the mix of facilities to be available to the community upon completion.
Recommendation(s)
The Committee is asked to RESOLVE that:
1. As part of the Transform Kingston Programme, the Council commits to the provision of a new community leisure centre in Kingston Town Centre subject to planning permission and subject to the financing being confirmed at budget Council on 1 March 2022 2. It is noted that the facilities mix for the Town Centre, as set out in section 7 of the report, is aligned to the need and latent demand identified in the draft Indoor Leisure Facilities Strategy 2022.
Benefits to the Community:
The Transform Kingston Programme is delivering heritage-led regeneration across a number of town centre assets including the delivery of the new leisure facilities replacing the now closed Kingfisher Leisure Centre. The proposed new community leisure centre for Kingston Town Centre will support the Council to meet the objectives of its borough-wide Leisure Strategy, providing the level of sports and recreation provision identified in the needs assessments whilst also meeting the wider regeneration ambitions of the Transform Kingston programme.
Key Points
A. Kingfisher Leisure Centre closed for routine maintenance in December 2019 as part of the cyclical works. Inherent structural issues with the roof were then uncovered which resulted in the centre not being able to reopen as scheduled.
B. In October 2020 the Response and Recovery Committee decided to proceed with assessment of the comprehensive redevelopment of a new leisure centre on the site, in preference to options involving repair of the existing leisure centre. In November 2020 the Response and Recovery Committee resolved that the Council assess a strategic business case for the Transform Kingston programme, including redevelopment of the leisure centre, and it allowed a capital sum to support feasibility assessment up to RIBA Stage 1 to inform the business case.
C. There was then an extensive phase 1 public engagement exercise over March and April 2021, and in May 2021 the Response and Recovery Committee considered an outline business case which included further explanation of the rationale behind the proposed redevelopment of the leisure centre. The Committee resolved to delegate authority for approval of any procurement strategies, in particular the replacement Kingfisher Leisure Centre, valued above £5m required to deliver the ambitions set out in the report, on the recommendation of the Commissioning Governance Board.
D. The Council has continued to engage with communities across the borough to understand what is most important to them in terms of the facilities and design of the new leisure centre.
E. A planning application for the demolition of the existing Kingfisher Leisure Centre was developed and presented to the Planning Committee in September 2021 and will be returned to the Planning Committee in due course. Work has also been progressing regarding the design of a new leisure facility on the site.
F. On 30 September 2021 the Corporate and Resources Committee resolved to include in the 2021/22 programme the additional capital budget of £40m for the leisure centre. The budget report for 2022/23 to 2025/56 (elsewhere on the agenda for this meeting) sets out the capital strategy and how the capital programme as a whole - including the leisure centre - will be funded. The final decisions on the capital strategy will be taken at the Budget Council on 1 March 2022.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.