Re-procurement of Housing Repairs, Maintenance and Major Works

Approved Committee 1 paper

Place Committee approved this item on Tuesday 21 March 2023. Below is the council's own wording, with the papers it was decided on.

Item107

Resolved

RESOLVED that: 1. the commissioning intention to procure a new contract for the provision of Housing Repairs, Maintenance and Major Works be approved; 2. authority be delegated to the Executive Director Place, in consultation with the relevant Portfolio Holder and the Commissioning Governance Board, to approve the detailed procurement strategy (Gateway 1) for the Repairs, Maintenance and Major Works Contract following the Council’s gateway process.
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Place Committee

Purpose of report

To approve the commissioning intention for the re-procurement of a new contract for the provision of Housing Repairs, Maintenance and Major Works; and to delegate authority to officers for approval of the detailed procurement strategy.

Recommendation(s)

The Committee is asked to RESOLVE that:

1. the commissioning intention to procure a new contract for the provision of Housing Repairs, Maintenance and Major Works be approved;

2. authority be delegated to the Executive Director Place, in consultation with the relevant Portfolio Holder and the Commissioning Governance Board, to approve the detailed procurement strategy (Gateway 1) for the Repairs, Maintenance and Major Works Contract following the Council’s gateway process.

Benefits to the Community:

The provision of housing repairs, maintenance and major works are key services for the housing department and Council as a whole. The services impact directly on the lives and wellbeing of residents living in over 6,000 Council owned homes as well as those living within c.400 private sector homes directly leased by the Council. The services will also help to deliver key Council priorities to reduce carbon emissions and essential landlord functions.

Procurement of a new provider against an updated specification/contract will ensure that these services offer best value, resilience and convenience for residents whilst supporting wider environmental benefits into the future.

Key Points

A. The Council has a housing stock of over 6,000 tenanted and leasehold properties. In addition the Council also provides services to over 400 privately rented homes leased by the Council and used as temporary accommodation.

B. The Council delivers general repairs, voids repairs, gas repairs and servicing, cyclical and planned maintenance and improvement services and works to these properties via a contract with a third party provider. Through this contract the Council delivers 15,000 repairs, 5,500 gas repairs and 6,000 servicing jobs every year.

C. This is a challenging time for Social Housing and particularly Repairs and Asset Management Services. Landlords are subject to much greater levels of scrutiny through the new Housing Regulator and Ombudsman. The Council also needs to ensure that the services meet the emerging requirements of the Fire Safety Act and the Building Safety Act. All of this is complicated by the ongoing uncertainty within the construction market which is driving strong cost inflation owing to shortages of labour and/or materials.

D. The existing contract with Axis Europe Plc was originally awarded in 2014 based on a Term Partnering Contract (TPC) for a period of seven years with an option to extend for a further three years. A service review was undertaken during 2019 which resulted in an agreed change to the repairs pricing model from Price per Property (PPP) to actual cost based on schedule of rates with a pain and gain element included (profit and risk sharing). This also led to a switch to the current Contractor providing a dedicated repairs call centre. Following the outcome of this review, it was agreed for the contract to proceed with the final option to extend for three years up to 31 March 2024 which was enacted.

E. The Council has considered the options available for continuing to provide the services at the end of the current contractual term. Options include extending the existing agreement with Axis, re-procuring the services through a competitive tendering process or bringing the services (in whole or in part) in-house. It is recommended that the Council seeks to reprocure the services against an updated specification/contract which will allow the opportunity to review and redesign services to be more resident focussed.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Re-procurement of Housing Repairs, Maintenance and Major WorksReport 130 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 15 attended
ED
Councillor Emily DaveyCo-Chair, present
RH
Councillor Roger HayesCo-Chair, present
PH
Councillor Peter HerlingerCo-Chair, in the Chair, present
IM
Councillor Ian MandersCo-Chair, present
RB
Councillor Rowena BassMember, present
MB
Councillor Mark BeynonMember, present
AB
Councillor Andrew BoltonMember, present
JD
Councillor Jackie DaviesMember, apologies, sent representative
MD
Councillor Mark DurrantMember, apologies, sent representative
IG
Councillor Ian GeorgeMember, present
JG
Councillor James GilesMember, present
MG
Councillor Mariana GoncalvesMember, present

All 15 on the meeting page

On this subject at Kingston upon Thames

Search all
  1. Re-procurement of Housing Repairs, Maintenance and Major WorksThis decision
  2. Re-procurement of the housing repairs and maintenance contractNoted

More from Kingston upon Thames Place Committee

All decisions
MeetingDecisionOutcome
23 Sep 2026 Coombe Lane West Proposed Zebra Crossing - Objections to Traffic Management OrderRESOLVED that: ( i ) the objections received in response to the published Traffic Management Order (TMO) for replacin... Decided Open
23 Sep 2026 Highway Infrastructure Asset Management PlanRESOLVED that the Highway Infrastructure Asset Management Plan and associated appendices, as set out in Annex 1 of th... Approved Open
23 Sep 2026 Seething Wells - Annual UpdateThe recommendations on page D1 of the agenda pack were not approved. The reporting requirements agreed under resoluti... Approved Open
23 Sep 2026 Motion referred by Council - “Every Councillor for Every Kind”After debate and amendments, the following motion was put to the vote and CARRIED . “ Council notes the “Every Counci... Decided Open
16 Jun 2026 Local Plan - Final Draft of the Local Plan (Regulation 19)RECOMMENDED TO COUNCIL that: 1. the ‘publication document’ for Regulation 19 statutory public consultation be approve... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies