RESOLVED that – 1. The prioritised planned schools capital maintenance works programme for 2024/25 set out in Tables 4 and 5 of the report, be approved; and 2. Authority be delegated to the Assistant Director of Property Investment and Development, in consultation with the Portfolio Holder for Children’s Services including Education, to agree changes to the programme within the year to ensure the appropriate application of the available funds.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
To seek approval of the projects that are proposed to form the schools capital maintenance programme for 2024/25. The report also provides an update on the works undertaken in 2023/24.
Recommendation(s)
The Committee is asked to RESOLVE that:
1. The prioritised planned schools capital maintenance works programme for 2024/25 set out in Tables 4 and 5 of the report, be approved; and
2. Authority be delegated to the Assistant Director of Property Investment and Development, in consultation with the Portfolio Holder for Children’s Services including Education, to agree changes to the programme within the year to ensure the appropriate application of the available funds.
Benefits to the Community:
Planned schools' capital maintenance programmes are developed to ensure that the provision of education and teaching takes place in suitable, fit for purpose and safe buildings and facilities to support high quality outcomes for young people.
Key Points
A. Delivering a planned schools capital maintenance programme is a key priority of the Council, ensuring that Local Authority maintained schools have the ability to provide suitable facilities for teaching and learning, with buildings in a satisfactory condition. The Council receives an annual grant; the Schools Condition Allocation (SCA) from the Department for Education, to support the costs of repair and maintenance works to those schools which it is responsible for.
B. There are 51 schools in the borough which provide primary and secondary education under a range of different governance models. Of these, 16 are Council maintained schools. The school estate is very diverse in terms of age, condition, energy efficiency and ownership/leasing arrangements. There is an ongoing need and increasing pressure to adequately maintain the condition and structures of school buildings and facilities together with key heating, mechanical, electrical and statutory systems.
C. The SCA is provided on an annual basis and can vary from year to year. To develop the programme, an assumed grant amount of £0.813m has been used which is based on an average of previous years’ allocations. The funding is required to cover all maintenance and major repair costs across all 16 schools which the Council is responsible for and, as such, is consistently over subscribed.
D. As a result, it is necessary to prioritise any spend with greater emphasis placed on those works necessary to keep school buildings safe and in good working order, i.e. by tackling poor building conditions and addressing compliance, energy efficiency and health and safety issues. This prioritisation is based on a range of data sources including building condition surveys, analysis of system life cycles and maintenance/repair callouts and spend and consideration of unfunded projects from previous years together with the direct views of individual schools on their own concerns.
E. The priority projects and reserve list, along with known other works and surveys which make up the 2024-25 programme are set out in Tables 4 and 5. There are eight priority projects with a total estimated value of c.£0.900m and a further five reserve projects with a total estimated value of c.£0.850m. As these schemes are developed there may well be issues which require a reconsideration or reprogramming and the recommendations allow for projects to be reallocated via delegation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Children and Young People's PlanRESOLVED that – 1. The progress to date of the delivery of actions set out in the Children and Young People’s Plan an...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.