Resolved
RESOLVED that the Council should progress with the investigation and setting up of habitat banks on Council owned land, in accordance with the arrangements set out in paragraphs 9 to 14 of the report.
Place Committee decided this item on Tuesday 24 June 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Council should progress with the investigation and setting up of habitat banks on Council owned land, in accordance with the arrangements set out in paragraphs 9 to 14 of the report.
To approve setting up of habitat banks in the Borough on Council owned nature reserve land to be able to offer biodiversity net gain (BNG) units for purchase as offsite units for developments in the Borough that are not able to meet their required BNG onsite.
Recommendation(s)
The Committee is asked to RESOLVE that the Council should progress with the investigation and setting up of habitat banks on Council owned land, in accordance with the arrangements set out in paragraphs 9 to 14 of the report.
Benefits to the Community:
High quality areas of nature can positively impact our health, well-being, economic and social development as well as increase resilience towards the challenges faced by climate change. These proposals would ensure that biodiversity in the Borough is retained and added to, financed as part of developments locally and perhaps more widely.
Key Points
A. Biodiversity Net Gain (BNG) legislation requires new developments (unless exempt) to increase biodiversity by a minimum of 10% across a proposed site. It is stated in the legislation that it should always be the preference for developers to achieve this within the boundary of each development. If onsite delivery is not possible then it is permitted to buy units offsite to make up any difference (“offsetting”). Should this also not be possible, then there is an option to contribute to a national credit fund.
B. Habitat banks allow landowners to sell biodiversity units to developers. The price of each unit is set to allow works on a defined area within the habitat bank to either create new biodiversity or to increase the quality of the existing space. The pricing of the units also includes the costs of monitoring and maintaining the new biodiversity over a period of 30 years.
C. Setting up a local habitat bank or banks would therefore allow the Council to raise funds to undertake and maintain improvements to nature reserves and, potentially, other green spaces in the Borough. This would support the aim that any biodiversity on development areas that is not able to be preserved and improved onsite can be reestablished elsewhere in the Borough.
D. The legal frameworks available to landowners to be able to offer biodiversity units for sale through habitat banks are described in this report along with a recommended route for one or two pilot habitat banks to be set up with minimum financial outlay for the Council in order to test the biodiversity unit market. The chosen framework would most likely be delivered through a concessions contract arrangement.
Context
1. Kingston’s Biodiversity Action Plan sets out the intention to be a borough that takes a leading role in protecting the environment, showcasing how a London borough can host an environment in which both humans and wildlife can thrive to mutual benefit, which can also contribute to the overall health of the planet. There are 12 Nature reserves in the Borough all of which have capacity to increase the richness of their biodiversity while creating valuable natural spaces for residents and visitors to enjoy as set out in Kingston’s Biodiversity Action Plan and accompanying Habitat and Flagship Species Action Plans.
2. For calculating BNG, the Statutory Biodiversity Metric uses three main types of habitat units set out below.
a. Area habitat units - these measure the biodiversity value of various land areas including grasslands, woodlands and wetlands b. Hedgerow units - these units assess the value of hedgerows and linear tree rows c. Watercourse units - linear water courses such as rivers and streams
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Habitat BanksReport | 207 KB | DownloadRead as text |
Follow Place Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Coombe Lane West Proposed Zebra Crossing - Objections to Traffic Management OrderRESOLVED that: ( i ) the objections received in response to the published Traffic Management Order (TMO) for replacin... | Decided | Open |
| 23 Sep 2026 | Highway Infrastructure Asset Management PlanRESOLVED that the Highway Infrastructure Asset Management Plan and associated appendices, as set out in Annex 1 of th... | Approved | Open |
| 23 Sep 2026 | Seething Wells - Annual UpdateThe recommendations on page D1 of the agenda pack were not approved. The reporting requirements agreed under resoluti... | Approved | Open |
| 23 Sep 2026 | Motion referred by Council - “Every Councillor for Every Kind”After debate and amendments, the following motion was put to the vote and CARRIED . “ Council notes the “Every Counci... | Decided | Open |
| 16 Jun 2026 | Local Plan - Final Draft of the Local Plan (Regulation 19)RECOMMENDED TO COUNCIL that: 1. the ‘publication document’ for Regulation 19 statutory public consultation be approve... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.