(1) That approval be given to the use of currently uncommitted £2.85m New Council Developments reserve against the broad categories of spend as detailed within the report. (2) That authority be delegated to the Director of Resources to allocate the reserve to specific activities within the broad categories of spend, and to report the use of the reserve in more detail within the quarterly revenue monitoring report.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
To seek Cabinet approval for investment in resources to support the council’s journey to a New Council, through use of the £2.85m New Council Developments Reserve.
2. Key points
2.1Over the next 3 years, the Council will need to undergo the largest change programme of a generation to achieve the fiscal reductions currently identified. The Council will need to realise a further £69 million in savings and cuts whilst redesigning services to mitigate the impacts on local people and business and do so in a way that meets Council priorities within the resources available. The scale of spending recommended is commensurate with the scale of that task. It should also be recognised that the existing pace of change will need to be accelerated to meet the timescales as the Council will have extinguished its reserves over this period. NC-15-001 2.2 The Council transformation programme has been supported for a number of months using a combination of officer time in programme and project boards, temporary programme and project management support resource, the allocation of significant amounts of officer time in addition to their day-to- day duties and some use of external supplier resources.
2.3The New Council Programme Board, Management Board, and Executive Team (ET) have increasingly raised the risks posed to the successful delivery of the achievement of a New Council through the continuation of the current support arrangements described above which are not considered sustainable.
2.4The February 2015 Budget Council agreed the re-designation of existing Council reserves totalling £3m, to a ‘New Council Developments’ reserve.
2.5Cabinet on 2 June re-affirmed the re-designation of £3m from existing Council reserves for New Council Developments reserve, as part of the final accounts process for 2014-15.
2.6The February 2015 Budget Council also approved specific commitments against this reserve totalling £150k, for Passivhaus and other energy renewable feasibility studies. This leaves a balance of £2.85m reserve currently uncommitted, for consideration in this report.
2.5Jacqui Gedman, Director of Place and the Chair of the New Council Programme Board, has considered the support needs identified and, on behalf of ET, is asking Cabinet to give delegated authority to the Director of Resources to allocate funding from the uncommitted £2.85m reserve against the following broad categories of spend, identified as critical to the overall success of the Council transformation programme over the 2015-18 medium term financial plan:
i. Procurement and provision of external support for activity within specific areas of the work to achieve New Council. For example, support for work on the ‘Economic Resilience’ and ‘Early Intervention and Prevention’ themed programmes. This support could be for a range of activity including programme management capacity, transformation/change activity or programme assurance.
ii. ‘Back-filling’ of officer roles where senior staff have been asked to dedicate a significant proportion of their working time to New Council activities and their further day-to-day duties must be delivered.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.