Item13:

Resolved

(1) That approval be given to the following key highways design principals as a basis for the design and development of the Kirklees West Yorkshire Transport Fund schemes; * Strategic and local needs will need to be carefully considered but where there is a strong evidence need for measures in support of overall benefits, strategic priorities will take preference over local ones. * Gateways will be created on our main roads on approaches to all main towns and urban centres. * Where schemes require third party land acquisition for highway purposes, such land will be acquired using compulsive purchase order powers where agreement cannot be reached by negotiation. Each case where a compulsive purchase order is considered necessary will be the subject of a further Cabinet report. * To improve the capacity and reliability of our existing transport corridors the use of management and road space will be considered and control measures proposed if congestion benefits will be achieved. Such measures to also consider potential mitigation measures for economic and environmental frontage activities. * The environmental and economic benefits of greening up our key transport corridors (green streets) is supported. (2) That it be noted that the outcome of the application of these principals on all our Kirklees West Yorkshire Fund Schemes would be included in future individual project reports as they are developed and presented to Cabinet for consideration/approval.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet

Purpose of report

To request Cabinet consider a number of forthcoming sensitive issues which are likely to arise from the development of the Kirklees WY Transport Fund schemes and to approve the key highway design principles set out in the recommendation

Some key issues around how we improve/develop our main transport corridors to deal with traffic congestion problems are likely to be publicly contentious and may lead to Cabinet having to make some difficult decisions. This paper sets out where the key issues may arise as well as a series of proposed principles to help mitigate concerns. 2. Background

2.1. The West Yorkshire Plus Transport Fund (WY+TF)

In its Local Plan and Economic Strategy documents, the Council has recently set out its ambitions for Kirklees to 2031. Accommodating the transport needs of 32,000 new jobs and 29,000 new homes in Kirklees means that improvements to our main roads and transport links is a real need for the district going forward.

To address this need Kirklees, together with Leeds, Bradford, Wakefield and Calderdale councils, York and the West Yorkshire Combined Authority have created a government funded West Yorkshire Transport Fund (henceforth known as WY+TF) which will facilitate major investment in transport to create an environment where economic growth can occur. This is to be achieved through the delivery of two complementary packages of schemes: Core Projects and Gateway Schemes.

Core Projects Projects which are the catalysts are and enablers of change, have the greatest direct short term economic impact (in terms of jobs supported per £ invested), and self-generate further funding to reinvest in more transformational projects.

Gateway Schemes that improve the entry Schemes are to our cities and towns and will often involve significant partner investment.

In July 2014, the Government announced that the West Yorkshire Combined Authority had secured funding to establish a £1bn fund over 15 years.

Funding for the first 6 years has been promised from the Government but the following 9 years funding is dependent upon successful delivery of the WY+TF programme and corresponding economic growth during the initial 5 years.

The principal objective of the WY+TF is to stimulate economic growth by improving connectivity across the region: connectivity in terms of people to jobs, businesses to businesses and goods to markets.

Other complementary objectives are:

 Improved accessibility to employment from the ‘deprived wards’ greater than the West Yorkshire average  Equitable distribution of improved accessibility geographically, with all Districts seeing an improvement greater than half the West Yorkshire average  A nil carbon change due to implementation of the overall package of schemes. Table 1 indicates the full list of schemes in Kirklees. The value of which is circa £150million.

2.2Proposed Principles

The key highway design principles that Cabinet are asked to consider are:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
West Yorkshire Transport Fund: Scheme PrinciplesReport 271 KB DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open