Resolved

(1) That, in regards to the General fund Revenue, (i) approval be given to proposals for £2.9m earmarked (risk) reserves drawdown to resource additional children’s services development costs in 2016-2017 (ii) the forecast £6.2m forecast revenue overspend position for 2016-2017 (as set out in Appendix A, Section 1) net of the reserves drawdown in ( i ), be noted (iii) the forecast outturn position on collection fund and forecast movements in reserves and balances in-year be noted (iv) consideration be given to officer proposals to bring the forecast £6.2m overspend at least in line with budgets by current year end, and other actions to build up available reserves to support the Medium term Financial Plan from 2017 onwards, and (v) officers be instructed to submit a report to Cabinet as part of the Medium Term Financial Plan update, with in-year and long term mitigating actions to bring spend back in line with available resources. (2) That, in regards to the Housing Revenue Account, ( i ) the forecast revenue outturn position for 2016-2017 (as set out in Appendix A, Section 1), be noted, and (ii) the forecast HRA reserves position at year end (as set out in Appendix B), be noted. (3) That the Council forecast capital outturn position for 2016-2017 be noted.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet, 22 pages

Purpose of the report

The purpose of this report is for Council to receive information on the Council’s 2016-17 forecast financial outturn position for General Fund revenue, Housing Revenue Account (HRA) and Capital Plan, as at Quarter 1 (month 3).

Summary

2.1The Council’s General Fund (net) revenue budget for 2016-17 was set at £310.8m. The Council’s forecast net revenue spend is £317.0m in 2016-17, resulting in an overspend of £6.2m, equivalent to 2.0%, against budget. The forecast net revenue spend position is summarised in Table 1 below.

1|Page Table 1 – Overview of 2016-17 general fund forecast revenue outturn position, as at Quarter 1 (month 3) :

Net Forecast Revenue Revenue Description Budget Outturn Variance £m £m £m Directorates 264.6 277.0 12.4 Reserves Drawdown - (2.9) (2.9) Directorate Sub-total 264.6 274.1 9.5 Central Budgets 44.9 42.5 (2.4) District Committee managed budgets 1.3 0.4 (0.9) Grand Total 310.8 317.0 6.2

2.2The forecast revenue outturn position set out in Table 1 above includes a proposed drawdown of “one-off” revenue funding (Corporate Reserves) in-year, totalling £2.9m, to offset Directorate budget pressures relating to Children’s service developments (see also, Section 3 below).

2.3Estimated movements in general fund balances and earmarked reserves in-year, including those referred to in paragraph 2.2 above, are forecast to total £36m. This includes a budget approved drawdown of £17.5m to support the delivery of a balanced budget in 2016-17.

2.4The balance of estimated in-year drawdowns total £18.5m. These relate to earmarked reserves previously set aside from previous years, to fund a number of specific “one-off” spend commitments materialising in the current year, including approved revenue rollover, staff severance costs (workforce restructure reserve) and specific projects funded from grants reserve, including Stronger Families Project. These are early year drawdown forecasts, and will continue to be reviewed and updated in subsequent quarterly monitoring reports to Cabinet.

2.5Overall, general fund corporate reserves are forecast to reduce from abut £93m as at April 2016, to about £57m as at 31 March 2017; equivalent to a 39% reduction over the year.

2.6These figures exclude statutory reserves held by the Council on behalf of local authority controlled schools. These reserves cannot be used by the Council for other purposes, and as at 31 March 2016 totalled about £20m.

2.7The £6.2m Quarter 1 projected overspend, if not corrected, will be a further call on available reserves.

2.8Of the remaining £57m forecast reserves at year end, there are a number of significant future year commitments against these intended to support the level of service re-design and change required within current approved budget plans, working to a New Council. These include set asides for future severance costs and Transformation reserves, plus the balance of deferred spend commitments against approved revenue rollover. These also included a minimum balances requirement of £5m. In total these come to about £28m, and effectively leaves just

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Revenue and Capital Financial Monitoring Report, Quarter 1, 2016-17Report 22 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 12 attended
DS
Councillor David SheardChair, present
SP
Councillor Shabir PandorCommittee Member, present
PM
Councillor Peter McBrideCommittee Member, present
NM
Councillor Naheed MatherCommittee Member, present
MK
Councillor Musarrat KhanCommittee Member, apologies
EH
Councillor Erin HillCommittee Member, present
VK
Councillor Viv KendrickCommittee Member, apologies
MA
Councillor Masood AhmedCommittee Member, present
GT
Councillor Graham TurnerCommittee Member, present
AW
Andrea WoodsideClerk, expected
YM
Yolande MyersClerk, expected
MS
Councillor Mohan SokhalGuest, in attendance

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open