1) That Council be advised that Cabinet supports the Draft Charging Schedule for consultation and submission to examination. 2) That approval be given to the schedule set out within the considered report, setting out the proposed consultation arrangements for the Draft Charging Schedule. 3) That authority be delegated to the Director of Place, in consultation with the Leader and Deputy Leader, to put in place any minor amendments to the consultation arrangements as set out in the considered report.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
This report requests approval to consult on the Community Infrastructure Levy (CIL) Draft Charging Schedule and proceed to examination alongside the Draft Local Plan.
The Draft Charging Schedule rates and charging zones can be found in Appendix A. Further explanation and requested actions are set out in this report. The future governance arrangements for distributing Community Infrastructure Levy revenue is not subject to this report and will need to be determined at a later date once the charge rates have been subject to independent examination.
2. Key points
The CIL is effectively a development tax that local planning authorities can implement to help pay for new infrastructure that is needed to support new development.
CIL rates have to be based on two main pieces of evidence;
An assessment of development viability across the district which tests the impacts of national and local planning policies and recommends CIL rates that will not render development unviable. The infrastructure assessment that supports the Local Plan and identifies what infrastructure schemes the CIL can help to fund.
The Council has commissioned consultants who have gathered evidence across Kirklees about the current viability of different types of development. The results and recommendations have provided the evidence for setting the Kirklees CIL Draft Charging Rates.
The infrastructure evidence supporting the Publication Draft Local Plan, in the form of the Infrastructure Delivery Plan and Infrastructure Delivery Plan Addendum, provide the justification for establishing a CIL charge to help pay for the infrastructure types and schemes identified.
a. Changes since the Preliminary Draft Charging Schedule Consultation
The first round of CIL consultation took place alongside the Draft Local Plan between 9th November 2015 and 1st February 2016. There were a total of 69 comments relating to the CIL Preliminary Draft Charging Schedule and its supporting evidence from a range of consultees including; developers, infrastructure providers and members of the public. The majority of comments were supportive or conditionally supportive, with 10 objections.
In response to comments received through the consultation and an update of viability evidence the Draft Charging Schedule includes some changes compared to the Preliminary Draft Charging Schedule. The specific changes are outlined below:
Reduction in the number of charging zones from 5 to 4, merging zones 1 & 2 of the Preliminary Draft Charging Rates. Revised charging zone boundaries based on updated housing market and viability evidence. Revised charge rate for charging zone 2 (From £60 to £20 per sq m for developments of more than 10 units). Following the Draft Charging Schedule consultation the document and supporting evidence will be submitted for examination where it will be considered whether the Council has struck an appropriate balance between:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.