Received an update on schemes approved by the Committee in 2015-16 and agreed funding of the following schemes in 2017-18: Coronation Street, Meltham improvements to pathways £13,464 Cornmill Estate, Slaithwaite improvements to pathways £14,960 Deacon Close, Meltham environmental works £6,000 Stony Lane, Honley improvements to pathways £9,700 Wessen Court, Marsden replace flagged area with tarmac, bench, artificial grass £7,800 Deacon Close, Meltham plant trees & shrubs to design out dog walking area £9,000 Various addresses retirement living schemes £68,000 Barnsley Road, Flockton clear shrubbery £12,350
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
Report to District Committee - Kirklees Rural, 7 pages
Purpose of report
1.1To provide an update on progress on the Estates and Environmental Works Budget 2016/17 following the recent Rural voting exercise held on the 26th September 2016 at the Methodist Mission in Huddersfield 2.0 Recommendations 2.1 District Committee members are asked to give consideration and approval to commission the schemes prioritised at the meeting.
2.2Note the progress made on Estate and Environmental Schemes approved for 2015/16.
3.0Key points
3.1The Estates and the Environmental works budget was previously known as the Tenant Led Budget.
3.2The Cabinet recently approved the re-introduction of the Budget with District Committees central to the governance of it. This allows a more strategic view and provides a more innovative use of funding with opportunities for joint funding using the other budgets if appropriate.
3.3The key aim of the budget is to encourage ideas, engage and involve decision making from a range of sources including councillors, tenants and leaseholders and residents.
4.0The Budget
4.1Any outcomes of projects commissioned must benefit in the main council tenants.
4.2The budget can be used to improve the letting ability of council properties, reduce nuisance, harassment, ASB and enhance the environmental impact of the estate.
4.3As it is an HRA budget it can be used for repair and maintenance of council housing, general tenancy and estate management, policy and management.
4.4The Budget cannot however be used to support the General Fund.
5.0Resource Allocation
District Number Budget Spent/ Budget Total budget Committee council 2015/16 Committed 2016 /17 available for properties new approvals 2016/17 Rural 3150 £97,179.00 £51,824.50 £97,179 142,522.50
5.1Any budget roll-over will be approached on the same basis as the General Fund and decisions are made as part of the annual budget process.
6.0Process and Approach 6.1 Previously, proposals were only prioritised once a year, the new approach is flexible and will allow district committees to approve any prioritised schemes twice per year if this is needed.
6.2Councillors, tenants and residents, leaseholders and officers have been advised that ideas can be proposed at any time. Special Forums can be held twice yearly to prioritise schemes and to fall in line with the District Committee dates.
6.3All submissions are worked up by KNH officers including surveying staff and other internal agencies such as highways to ensure that costs are accurate, and schemes are viable and meet the HRA criteria.
6.4Area Forum members including TRA representatives, Councillors, Lone Voices and Leaseholders receive written communication outlining the process for submissions including following:
Budget available How ideas would be gathered Criteria for the use of the budget and work that could be carried out The deadline for bids in readiness for the Special Forum. The Voting Meeting for Rural was held on the 26th September 2016 where representatives were presented with the submissions and voted on the priorities as outlined in Appendix 1.
7.0Implications for the Council
7.1Strategic planning and larger schemes which are linked to other funding initiatives are generally more complex and takes longer to be implemented.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.