That approval be given to the preparation of a programme of works to reflect Asset Management principles and maximise grant funding to contribute to and compliment the Council’s Corporate Plan, and the Council priorities of early intervention and economic resilience.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
For Cabinet to consider the Highways Network priorities, in the context of reducing funding and a need to adhere to an asset management methodology.
2. Key points
2.1DFT (Department for Transport) funding for Highway maintenance composes 3 elements:
i. Needs
Grant award that simply reflects the length of carriageway. It does not reflect condition. This element is approximately 80% of the total funding. ii. Incentive
This is top-sliced (at a regional level) which has reduced the available grant. Authorities must demonstrate best practice of Asset Management in order to access this funding.
Kirklees has achieved band 2 status in Asset Management and is working towards band 3 to maximise our incentive allocation.
Achievement of band 3 increases the grant as follows:
Year 2017/18 2018/19 2019/20 £51,000 £307,000 £512,000
Achievement of band 3 this year will be difficult and the results will not be known until March 2017.
iii. Challenge Fund
Kirklees was one of only 31 successful bids in the initial tranche (2015/16) securing £1.6m of funding from the top-sliced grant.
A second tranche is programmed for submission this year 2017/18; details are awaited of the bid criteria.
2.2Additional Funding
Grant Funding
A pothole grant of £452,000 was previously awarded to local authorities which is anticipated to continue for the next 4 years.
Borrowing
In addition to the grant, Kirklees allocates c£1.8m (ave.) of capital borrowing to Highways.
Note: Proposed budget reductions may see this fall.
Investment totals currently therefore (excluding roll over): 2017/18 2018/19 2019/20 Needs level 2 £5,895,000 £5,639,000 £5,434,000 Potholes Grant £452,000 £452,000 £452,000 Borrowing (Kirklees) £1,967,000 £1,707,000 £1,912,000 £8,314,000 £7,798,000 £7,798,000
So the level of investment £8.3m needs to be set in context of the HMEP methodology:
Current backlog :- £76.7m Estimated time to clear back-log:- 10yrs Annual average budget shortfall :- £8m The resulting frequency of road surfacing:- 185yrs on unclassified roads Kirklees must ensure that all monies invested in the Asset reflect the best practice methodologies included in the Highway Maintenance Asset Plan, this is audited via the questionnaire and has to be authorised by the Section151.
It is clear that as funding resources reduce pressure will increase on the network and road condition will deteriorate further.
2.3Performance
Funding and Asset Management decisions are reflected in road conditions, these are measured at a regional level. The Appendix attached illustrates the % of roads requiring urgent maintenance, rated as “red” by assessment of the 5 West Yorkshire Districts.
Over the 9 year period, Kirklees A, B & C roads are in slightly poorer condition compared to West Yorkshire. Unclassified roads are consistently measured as being in better condition.
Investment decisions should ensure that our A B+C road condition improves.
2.4Repair of potholes
The Council is clear that our residents are concerned about the condition of the roads in Kirklees. In particular the time it takes for potholes to be repaired and the perception of the quality of the repair that takes place.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.