Resolved
That approval be given for ground stabilisation remedial works to be undertaken on the A635, Holmfirth Road, Shepley.
Cabinet approved this item on Tuesday 25 July 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That approval be given for ground stabilisation remedial works to be undertaken on the A635, Holmfirth Road, Shepley.
For the Cabinet to consider the option for the proposed ground stabilisation at A635 Holmfirth Road, Shepley.
Key Decision - Is it likely to result in Yes spending or saving £250k or more, or to have a significant effect on two or more electoral wards?
Key Decision - Is it in the Council’s Key Decision - Yes Forward Plan (key decisions and private Private Report/Private Appendix - No reports?)
The Decision - Is it eligible for call in by Yes Scrutiny?
Date signed off by Strategic Director & Naz Parkar - 06.07.17 name
Is it also signed off by the Service Director for Finance, IT and Debbie Hogg - 06.07.17 Transactional Services
Is it also signed off by the Service Director (Legal Governance and Julie Muscroft - 06.07.17 Commissioning)?
Cabinet member portfolio Cllr Musarrat Khan - Highways and Neighbourhoods
Electoral wards affected: Kirkburton Ward councillors consulted: Cllr John Taylor, Cllr Richard Smith and Cllr Bill Armer Public or private: Public 1. Summary
The A635 Holmfirth Road in Shepley is a major classified route linking the south of Kirklees with the M1 and neighbouring towns including Penistone, Barnsley and the City of Wakefield.
The A635 Holmfirth Road near its junction with Rowgate (see location plan) has been subject to an ongoing ground movement over the past 65 years. This has caused the highway and a substantial retaining wall that supports it to fail on several occasions leading to the partial closure of the road for many months, pending the implementation of interim/ semi-permanent remedial measures.
The proposed remedial works to mitigate the ground movements and stabilise the highway including its retaining structures are based on the outcome of extensive site investigation that has been undertaken to identify the underlying cause/s of the movement so as to devise an appropriate and effective remedial scheme to resolve the highway subsidence problem.
The current proposals include the construction of large bored reinforced concrete piles over the affected section (Approx 60m in length) to mitigate the ground movements and stabilise the highway and the substantial retaining wall supporting it. The works will be largely funded by additional funding secured through a successful Challenge Fund bid by Highways in 2015.
The proposed works can be constructed whilst maintaining a single lane shuttle working to minimise disruption to the local community and traffic.
2. Information required to take a decision
The A635 Holmfirth Road is a principal route that links the south of Kirklees with the M1 and neighbouring towns including Penistone, Barnsley and the city of Wakefield.
The affected section of A635 Holmfirth Road near its junction with Rowgate and the retaining wall that supports it, has been subject to periodic remedial measures due to subsidence and partial failure over the past 65 years. Various engineering interventions have been implemented to address the ongoing ground movements which manifest itself as significant settlement in the highway and the retaining wall, together with the development of deep longitudinal cracks in the road surface, but these have largely failed to address the underlying root of the problem. A comprehensive ground investigation recently completed at this site has now established the presence of a deep slip plane below the highway, which often becomes mobilised following a sustained heavy down pour and is now considered to be the underlying mechanism behind the ongoing ground movement.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Proposed remedial works for ground stabilisation at A635 Holmfirth Road, ShepleyReport | 7 pages | DownloadRead as text |
Follow Cabinet at Kirklees and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... | Noted | Open |
| 3 Nov 2026 | 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... | Approved | Open |
| 3 Nov 2026 | 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... | Approved | Open |
| 6 Oct 2026 | 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... | Noted | Open |
| 6 Oct 2026 | 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.