1) That approval be given to (i) establishing, within the Strategic Regeneration Capital Budget, a rolling ‘WYTF Land Acquisition Fund’ with an initial allocation of £0.85m (ii) commencing negotiations with land owners for land required to deliver the A629 Halifax Road (Phase 5) project (iii) developing the WYTF A629 Halifax Road (Phase 5) project to an outline business case stage with a target date of submission in October 2017 (iv) seeking funding approval via the WYCA Investment Committee to continue scheme development in order to achieve full business case status which would permit delivery of the scheme, when accepted, and (v) the submission of a report to Cabinet seeking consideration of full scheme approval and implementation, with authorisation in a similar timeframe to (iv), to enable the WYTF A629 Halifax Road Phase 5 to progress to construction. 2) That the exercise of the authority for the Council to acquire parcels of land for highway purposes, where the acquisition price is between £250,000 and £500,000 be delegated to the Service Director (Economy, Regeneration and Culture) to be exercised by the Service Director, in consultation with the relevant Cabinet Portfolio Holder.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
Cabinet to consider underwriting land acquisition costs until finance is subsequently secured from WY+TF and costs reimbursed. It is suggested that the Council establishes a rolling ‘WY+TF Land Acquisition Fund’
Key Decision - Is it likely to result in spending or Yes saving £250k or more, or to have a significant effect on two or more electoral wards? All Wards Land Acquisition Costs may exceed £250k . Key Decision - Is it in the Council’s Forward Yes Plan (key decisions and private reports?) July 24 2017
The Decision - Is it eligible for call in by Yes Scrutiny?
Date signed off by Strategic Director & name Naz Parkar - 10.08.17
Is it also signed off by the Service Director - Finance, IT, and Transactional? Debbie Hogg - 02.08.17
Is it also signed off by the Service Director - Legal, Governance and Commissioning? Julie Muscroft - 09.08.17 Cabinet member Economy Cllr Peter McBride Economy - Strategic Planning Regeneration and Transport
Cllr Naheed Mather Economy - Strategic Housing, Regeneration and Enforcement
Electoral wards affected: All
Ward councillors consulted: None
Public or private: Public Report
Summary
1.1Cabinet to consider underwriting land acquisition costs until finance is subsequently secured from WY+TF and costs reimbursed.
2. Information required to take a decision
2.1A report ‘West Yorkshire + Transport Fund (WY+TF) - Scheme Principles’ was submitted to Cabinet on the 9th February 2016 requesting Cabinet to consider a number of forthcoming sensitive issues which are likely to arise from the development of the Kirklees WY+TF schemes. One of the issues and areas of CAB - 17 - 020 - West Yorkshire +Transport Fund (WY+TF) - Land Acquisition Fund sensitivity raised was the need to acquire third party land to enable scheme delivery.
2.2The Cabinet report set out that the application of these issues on Kirklees WY+TF schemes which are mainly highway improvement schemes, will be included in future individual project reports as they are developed and presented to Cabinet for consideration/approval.
2.3Projects and Programmes being delivered under the management of the West Yorkshire Combined Authority for the WY+TF, have to progress through five activity stages prior to achieving final scheme approval:
a. Expression of Interest b. Case Paper c. Outline Business Case d. Full Business Case e. Finalise Costs/Approval to Construct.
When the WY+TF was initially established, the Combined Authority determined that funds to acquire land would only be released for schemes after Full Business Case approval was achieved.
2.4However this condition has now been relaxed and as such, we can now seek funding for the acquisition of land at the Outline Business Case stage which allows officers to commence negotiations with the land owners to try and secure the land, at an earlier stage which could be beneficial.
2.5Whilst the Council will endeavour to purchase land in line with the available funding, there may be a need to secure land at short notice, for example where land or property comes onto the market and it would be in the Council’s interest to acquire at that time. Such a situation could mean that acquisitions are undertaken potentially at the Council’s risk.
2.6As funding for acquiring land is deferred and based on costs incurred, the ability to draw down the funding from WY+TF will be given via a Funding Agreement which can only be claimed upon completion of the purchase.
2.7This means that each project promotor (i.e. the local Authority) will have to put mechanisms in place to underwrite land acquisition costs themselves in the short term.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.