That the content of the report be noted, in particular (i) the progress made on scheme development to date and the upcoming programme milestones (ii) the intention and reasons for employing a ‘twin track’ approach to land assembly, that any decisions regarding compulsory purchase would only be used as a last resort to secure the assembly of all the land needed for the implementation of a scheme, and that if a compulsory purchase is required a scheme specific report will be submitted to Cabinet prior to commencing any statutory processes (iii) the intention to write to all affected owners and occupiers of property/land in relation to the Halifax-Huddersfield A629 corridor Phase 5 scheme in order commence land negotiations (iv) in regards to Longroyd Bridge, the requirement to demolish no.s 1-7 Longroyd Lane subject to key stakeholder engagement which would include Historic England and putting in place the necessary consents and (v) the development of a consultation strategy and launch of an information website.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
To update Cabinet on progress made on the Kirklees schemes within the West Yorkshire plus Transport Fund (WY+TF) programme.
Key Decision - Is it likely to result in spending or No saving £250k or more, or to have a significant effect on two or more electoral wards? Key Decision - Is it in the Council’s Forward No Plan (key decisions and private reports?) The Decision - Is it eligible for call in by Yes Scrutiny?
Date signed off by Strategic Director & name Naz Parkar - 28.11.2017
Is it also signed off by the Service Director - Finance, IT and Transactional? Debbie Hogg - 01.12.2017
Is it also signed off by the Service Director - Legal Governance and Commissioning? Julie Muscroft - 08.12.2017
Cabinet member Economy Cllr Peter McBride Strategic Planning, Regeneration and Transport
Cllr Naheed Mather Strategic Housing, Regeneration and Enforcement
Electoral wards affected: All
Ward councillors consulted: None
Public or private: Public
Summary
1.1Progress reports are provided for a number of our WY+TF schemes currently in development. The intention is to provide regular updates on progress of the WY+TF.
1.2The report introduces the agreed Assurance Process that each and every scheme has to go through. The Assurance Process (Appendix 1) is administered by the West Yorkshire Combined Authority (WYCA) Portfolio Management Office.
1.3For each of our WY+TF schemes this report gives an indication if there is likely to be a requirement for
Land acquisition; WY+TF update 21 November 2017 Accommodation work on private property; and Measures to manage road space.
2. Information required to take a decision
2.1Kirklees, together with the other four WY district councils, the WY Combined Authority and York, have created a government funded West Yorkshire plus Transport Fund that will facilitate major investment in transport to create an environment where economic growth will occur across WY. This is to be achieved through the delivery of two complementary packages of schemes
Core Projects
Projects which are the catalysts and enablers of change, have the greatest direct short term economic impact (in terms of jobs supported per £ invested), and self-generate further funding to reinvest in more transformational projects.
Gateway Schemes
Schemes that improve the entry to our cities and towns and will often involve significant partner investment.
2.2In July 2014, the Government announced that the West Yorkshire Combined Authority had secured funding to establish a £1bn fund over 15 years.
Funding for the first 6 years has been secured from the Government but the following 9 years funding is dependant up successful delivery of the WY+TF programme and corresponding economic growth during the initial 5 years which equates to circa £420m of spend.
2.3As a result of this challenging timeframe focus for the WY+TF is now firmly on scheme delivery. Updates are given for the Kirklees schemes detailed in Table 1.
2.4For each of our transportation schemes there is an agreed Assurance Process that each and every scheme has to go through. The Assurance Process (Appendix 1) is administered by the West Yorkshire Combined Authority (WYCA) Portfolio Management Office.
2.5To date Cabinet has received two reports which relate to the West Yorkshire plus Transport Fund. On 9th February 2016 Cabinet approved the ‘West Yorkshire Transport Fund – Scheme Principles’ report which highlighted a number of key highway design principles that could be used as a basis for the design and development of the Kirklees WY+TF schemes, these were
Balancing strategic needs against local concerns; Creating “Gateways” for our main town and urban centres; The acquisition/appropriation of land for highway purposes; The future use and management of the road-space of our key transport corridors; and The environmental and economic benefits of greening up our key transport corridors (Green Streets).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.