Cabinet, Tuesday 19 December 2017 at 4.00pm

9

Noted Executive 1 paper

Cabinet noted this item on Tuesday 19 December 2017. Below is the council's own wording, with the papers it was decided on.

Item9:

Resolved

That the content of the report be noted, in particular (i) the progress made on scheme development to date and the upcoming programme milestones (ii) the intention and reasons for employing a ‘twin track’ approach to land assembly, that any decisions regarding compulsory purchase would only be used as a last resort to secure the assembly of all the land needed for the implementation of a scheme, and that if a compulsory purchase is required a scheme specific report will be submitted to Cabinet prior to commencing any statutory processes (iii) the intention to write to all affected owners and occupiers of property/land in relation to the Halifax-Huddersfield A629 corridor Phase 5 scheme in order commence land negotiations (iv) in regards to Longroyd Bridge, the requirement to demolish no.s 1-7 Longroyd Lane subject to key stakeholder engagement which would include Historic England and putting in place the necessary consents and (v) the development of a consultation strategy and launch of an information website.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet, 15 pages

Purpose of report

To update Cabinet on progress made on the Kirklees schemes within the West Yorkshire plus Transport Fund (WY+TF) programme.

Key Decision - Is it likely to result in spending or No saving £250k or more, or to have a significant effect on two or more electoral wards? Key Decision - Is it in the Council’s Forward No Plan (key decisions and private reports?) The Decision - Is it eligible for call in by Yes Scrutiny?

Date signed off by Strategic Director & name Naz Parkar - 28.11.2017

Is it also signed off by the Service Director - Finance, IT and Transactional? Debbie Hogg - 01.12.2017

Is it also signed off by the Service Director - Legal Governance and Commissioning? Julie Muscroft - 08.12.2017

Cabinet member Economy Cllr Peter McBride Strategic Planning, Regeneration and Transport

Cllr Naheed Mather Strategic Housing, Regeneration and Enforcement

Electoral wards affected: All

Ward councillors consulted: None

Public or private: Public

Summary

1.1Progress reports are provided for a number of our WY+TF schemes currently in development. The intention is to provide regular updates on progress of the WY+TF.

1.2The report introduces the agreed Assurance Process that each and every scheme has to go through. The Assurance Process (Appendix 1) is administered by the West Yorkshire Combined Authority (WYCA) Portfolio Management Office.

1.3For each of our WY+TF schemes this report gives an indication if there is likely to be a requirement for

 Land acquisition; WY+TF update 21 November 2017  Accommodation work on private property; and  Measures to manage road space.

2. Information required to take a decision

2.1Kirklees, together with the other four WY district councils, the WY Combined Authority and York, have created a government funded West Yorkshire plus Transport Fund that will facilitate major investment in transport to create an environment where economic growth will occur across WY. This is to be achieved through the delivery of two complementary packages of schemes

Core Projects

Projects which are the catalysts and enablers of change, have the greatest direct short term economic impact (in terms of jobs supported per £ invested), and self-generate further funding to reinvest in more transformational projects.

Gateway Schemes

Schemes that improve the entry to our cities and towns and will often involve significant partner investment.

2.2In July 2014, the Government announced that the West Yorkshire Combined Authority had secured funding to establish a £1bn fund over 15 years.

Funding for the first 6 years has been secured from the Government but the following 9 years funding is dependant up successful delivery of the WY+TF programme and corresponding economic growth during the initial 5 years which equates to circa £420m of spend.

2.3As a result of this challenging timeframe focus for the WY+TF is now firmly on scheme delivery. Updates are given for the Kirklees schemes detailed in Table 1.

2.4For each of our transportation schemes there is an agreed Assurance Process that each and every scheme has to go through. The Assurance Process (Appendix 1) is administered by the West Yorkshire Combined Authority (WYCA) Portfolio Management Office.

2.5To date Cabinet has received two reports which relate to the West Yorkshire plus Transport Fund. On 9th February 2016 Cabinet approved the ‘West Yorkshire Transport Fund – Scheme Principles’ report which highlighted a number of key highway design principles that could be used as a basis for the design and development of the Kirklees WY+TF schemes, these were

 Balancing strategic needs against local concerns;  Creating “Gateways” for our main town and urban centres;  The acquisition/appropriation of land for highway purposes;  The future use and management of the road-space of our key transport corridors; and  The environmental and economic benefits of greening up our key transport corridors (Green Streets).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
West Yorkshire plus Transport Fund Scheme UpdateReport 15 pages DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies