Cabinet, Tuesday 23 January 2018 at 4.00pm

13

Noted Executive 1 paper

Cabinet noted this item on Tuesday 23 January 2018. Below is the council's own wording, with the papers it was decided on.

Item13:

Resolved

(1) That it be noted that a Prior Notification of Demolition application for the demolition of the Clock Tower at Mount Pleasant Primary School has been submitted. (2) That approval be given to (i) the allocation of an additional £125k Basic Need Capital Grant funding to the new Mount Pleasant Primary School scheme and (ii) the authorisation of a revised Section 151 letter to be issued if required by the ESFA.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet

Purpose of report

To update Members on the current position with regards to the new build school for Mount Pleasant Primary, outline the need for further works and to consider the financial implications for the Council.

Is it likely to result in spending or No saving £250k or more, or to have a significant effect on two or more electoral wards? Is it in the Council’s Forward Plan? No

Is it eligible for “call in” by Scrutiny? Yes

Date signed off by Strategic Director and name Naz Parkar - 15.01.2018

Is it also signed off by the Service Director for Finance, IT & Transactional Services? Debbie Hogg - 15.01.2018

Is it also signed off by the Service Director - Legal, Governance & Commissioning? Julie Muscroft - 11.01.2018

Cabinet member portfolio Corporate - Cllr Masood Ahmed Cllr Graham Turner

Electoral wards affected: Newsome/Crosland Moor and Netherton Ward councillors consulted: Yes

Public or private: Public

Summary

1.1Mount Pleasant Primary School is currently being re-built as part of the Government’s Priority Schools Building Programme (PSBP). Much of the old school has been demolished and a new build school was handed over to the Council on 27th October 2017. The project is now entering its final stages with the demolition of the remaining defunct accommodation and the completion of external works by July 2018. 1 1.2 This report provides an update on the project and seeks approval from Members to allocate an additional £125K of Council funding from its Basic Need capital grant to provide enhancements to the external areas not covered by the PSBP.

2. Information required to take a decision.

(a) Background

2.1Due to the rising backlog of condition works at Mount Pleasant Primary School, in 2011 Kirklees Council submitted a successful bid to the Government’s PSBP for the replacement of Mount Pleasant Primary with a new build school.

2.2During 2012-14 the Council and the Education and Skills Funding Agency (ESFA) worked together to develop an agreed project and in June 2014, following Cabinet approval in March 2014, a Section 151 letter was agreed between the Council and the ESFA which committed the ESFA to the clearance of the existing site and its replacement with a new build school at an estimated investment value of £8-10M.

2.3In March 2015 an update report to Cabinet authorised the project to continue and provided officers with delegated authority to progress the demolition of the former Lockwood Community Centre and associated Clock Tower in its entirety, provided that interested parties were first given the opportunity to submit funded proposals for the retention and future use of the Clock Tower structure. This opportunity was given and no proposals were either received by the submission closure date in autumn 2015 or subsequent to this.

2.4On 8th March 2016 Cabinet approved a capital injection of up to £425K by the Council into the ESFA project to address concerns raised by officers and the school’s Senior Management Team regarding pupil movements around the building, arrangements for disabled access and sick pupils and pupil/parent access to the site and building. Cabinet delegated authority to officers to agree improvements to the existing design of the building such as the widening of corridors and the creation of a larger and more noticeable main entrance, plus improvements to access to the site. This was to be funded from Section 106 contributions (£238K) and Basic Need capital grant (£187K).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on the Priority School Building Programme Rebuild of Mount Pleasant PrimaryReport 178 KB DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open