Cabinet, Tuesday 20 March 2018 at 4.00pm

9

Approved Executive 1 paper

Cabinet approved this item on Tuesday 20 March 2018. Below is the council's own wording, with the papers it was decided on.

Item9:

Resolved

That the recommendations within the report for the large scheme road surfacing programme, be approved.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet

CAB -18 - 010

Name of meeting CABINET Date: 20th March 2018

Title of report 2018/19 Road Surfacing Programme (large schemes)

Purpose of Report This is a key decision to seek approval for a programme of road resurfacing schemes for 2018/19. These are schemes that each requires spend of more than £250,000 on the road network

Key Decision - Is it likely to result in Yes spending or saving £250k or more, or to Greater than £250k have a significant effect on two or more electoral wards? Key Decision - Is it in the Council’s Yes Forward Plan (key decisions and private reports?

The Decision - Is it eligible for call in by Yes Scrutiny?

Date signed off by Strategic Director & Karl Battersby - 6.03.18 name

Is it also signed off by the Service Debbie Hogg - 7.03.18 Director, Finance, IT, and Transactional Eamonn Croston for and on behalf of Services?

Is it also signed off by the Service Director Legal, Governance and Julie Muscroft - 9.03.18 Commissioning? Cabinet member portfolio Corporate - Cllr Graham Turner/Cllr Musarrat Khan

Electoral wards affected: Batley East, Batley West, Greenhead, Kirkburton, Mirfield, Newsome.

Ward councillors consulted: Cllr Mahmood Akhtar, Cllr Fazila Loonat, Cllr Habiban Zaman, Cllr Gwen Lowe, Cllr Marielle O’Neil, Cllr Shabir Pandor, Carole Pattison, Cllr Mohan Sokhal, Cllr Sheikh Ullah, Cllr Bill Armer, Cllr Richard Smith, Cllr John Taylor, Cllr Martyn Bolt, Cllr Vivien Lees-Hamilton, Cllr Kath Taylor, Cllr Karen Alison, Cllr Andrew Cooper, Cllr Julie Stewart- Turner

Public or private: PUBLIC

2018/19 Road Surfacing Programme CAB -18 - 010

1. Summary Road resurfacing works are proposed within the Highways Capital plan for the following roads. The extent of works is shown on the attached plans.

Scheme From To Ward Scheme Programme Plan Estimate A 62 Castlegate, Manchester Trinity St Newsome £420,000 Principal Roads DS/49/99999/CAB Huddersfield Rd A652 Bradford Road, North Street Rouse Mill Batley East £680,000 Principal Roads DS/25/23673/CAB Batley Lane A644 Huddersfield Steanard La Knowl Rd Mirfield £400,000 Principal Roads DS/49/48337/CAB Road, Mirfield C641 Luck Lane, Church St Link Road Greenhead £270,000 Roads Connecting DS/25/64492/CAB Paddock Communities C574 Farnley Rd, Storthes Hall Manor Rd Kirkburton £310,000 Roads Connecting HM25/64480/CAB Farnley Tyas Lane Communities C996 Newsome Road Jackroyd La Bridge St Newsome £250,000 Roads Connecting South, Newsome Communities 25/64491/CAB Healey Lane, Batley Batley Rd B6123 Batley £370,000 Local Community DS/25/43259/CAB Healey La West Roads Table 1

2. Information required to take a decision 2.1 Annual surveys of road condition identify the backlog of road repairs. The current backlog by road classification is shown in table 2. These schemes will repair roads and improve the backlog of repair.

Road type backlog Year on year performance A Roads 7km (3%) improving B Roads 3km (3%) improving C Roads 6km (4%) improving Other roads (U) 220km (15%) declining Table 2 2.2 The funding source is a grant through the Local Transport Plan (LTP) Grant allocation. Road surfacing schemes consider the needs of all road users hence elements of road safety e.g improved skid resistance, network management, drainage etc are included in the schemes.

2.3The schemes will be discussed during Utility Liaison Meetings by the Streetscene - Streetworks Co-ordinator and any necessary utility works will be carried out prior to the resurfacing. A Section 58 Protection has been issued for the extents of the proposed surfacing, which will provide a 5 year protection from utility excavations unless in an emergency situation.

2.4We are aware that these schemes may cause significant difficulties for through traffic. Officers will be in discussions with local councillors about the proposed improvements, and how delay and disruption can be minimised

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2018/2019 Road Surfacing Programme (large schemes)Report 5.5 MB DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies