(1) Approval was given for the Council to enter into a Grant Agreement with the West Yorkshire Combined Authority for additional funding of £4,116,295 for the purposes of enabling the West Yorkshire Transport Fund A629 Halifax Road Phase 5 project to move to the Full Business Case stage; (2) Authority be delegated to the Strategic Director for the Economy and Infrastructure to negotiate and agree the terms of the Grant Agreement referred to in paragraph 6.1 of the report, with the West Yorkshire Combined Authority; (3) Authority be delegated to the Service Director Legal Governance & Commissioning to enter into and execute the Grant Agreement referred to in paragraph 6.1 of the report together with any documents and agreements that are ancillary to it; (4) Authority be given to serve formal requisitions for information for a CPO under Part XII Acquisition, Vesting and Transfer of Land etc., namely Sections 239, 240 and 246 of the Highways Act 1980; (5) Authority be delegated to the Strategic Director for Economy and Infrastructure to implement the West Yorkshire Transport Fund A629 Halifax Road Phase 5 project improvement works in the event that ( i ) either all third party land that is required for the project has been acquired or any CPO has been confirmed; and (ii) the Full Business Case has been approved by the West Yorkshire Combined Authority (WYCA) and funding from the WYCA has been confirmed (iii) when the necessary Traffic Regulation Orders have been made.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
To seek formal approval from Cabinet for the WY+TF A629 Halifax Road Phase 5 project, which aims to reduce congestion, improve air quality and drive economic growth, to progress to construction (Subject to Full Business Case approval) and for the Council to progress preliminary preparation of a CPO.
Key Decision - Is it likely to result in Yes spending or saving £250k or more, or to have a significant effect on two or more Affects Lindley and Greenhead wards. electoral wards? Cost of scheme £12.09m Key Decision - Is it in the Council’s Yes Forward Plan (key decisions and private reports?) 13 Sep 2018
The Decision - Is it eligible for call in by Yes Scrutiny?
Date signed off by Strategic Director & Karl Battersby - 27.09.18 name
Is it also signed off by the Service Eamonn Croston - 24.09.18 Director Finance?
Is it also signed off by the Service Julie Muscroft - 21.09.18 Director Legal Governance and Commissioning? Cabinet member portfolio Cllr Peter Mcbride - Economy
Electoral wards affected: Lindley and Greenhead
Ward councillors consulted:
Cllr Carol Pattison, Cllr Mohan Sokhal, Cllr Sheikh Ullah, Cllr Cahal Burke, Councillor Richard Eastwood, Cllr Gemma Wilson
Public or private: Public 1. SUMMARY
1.1Congestion, long journey times and poor air quality is currently experienced along the A629 between Huddersfield and Halifax town centres. Kirklees Council, in partnership with the West Yorkshire Combined Authority, is working toward a programme of transport improvements at key junctions between Huddersfield ring road and Ainley Top roundabout that will seek to address these issues and drive economic growth.
1.2The objectives of the project are shown in Table 1 below:
Table 1 – Project Objectives
1 Improve accessibility between Huddersfield and Halifax and to the M62 by reducing congestion, thus improving journey time reliability, and reduce journey times between the ring road and Ainley Top roundabout by at least 1 minute for all road users by 2022.
2 Job retention and growth in the wider area with the creation of 465 indirect jobs by 2030 and to support delivery of the Lindley Moor West and East Enterprise Zones.
3 Support housing growth in Lindley area and west Huddersfield generally (1230 homes) and enable the delivery of up to 780 dwellings within the vicinity of the corridor by 2030.
4 Improve air quality for local residents by contributing to a target reduction of NOx levels by 10µg/m3 and a target PM 2.5 particulates to 7µg/m3.
5 Contribute to improving GVA across West Yorkshire. (early modelling suggested a GVA increase of £10.9m by 2030)
1.3The Phase 5 project was submitted to the WYCA in January 2018 and secured Outline Business Case (OBC) approval on 10 March 2018 releasing an additional £4,116,295 of Grant funding to progress the project to Full Business Case (FBC) stage.
1.4The FBC stage will see the project progress through detailed design to tender stage for construction of the works. Providing that the project remains Value for Money, after return of tenders, then the project will likely achieve FBC approval where funds will be released to construct the scheme. 1.5. The Economic benefits of the project at OBC stage were shown to be at least £75m providing Very High Value for Money (based on Department for Transport criteria).
1.6The proposed improvements will require third party land to accommodate widening of the existing highway.
1.7An essential element of securing FBC approval is to demonstrate that the necessary interests in land and, where necessary, creation of new rights over land, needed, to enable the proposed highway improvements and mitigation measures to be delivered, can be obtained.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.