Resolved
That approval be given for Kirklees Neighbourhood Housing to progress to the delivery of the 5 year Housing Revenue Account Capital Plan.
Cabinet approved this item on Tuesday 13 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That approval be given for Kirklees Neighbourhood Housing to progress to the delivery of the 5 year Housing Revenue Account Capital Plan.
To consider the adoption of a 5 year capital improvement plan to Council Housing, approve the approach, associated budgets and programmes.
Key Decision - Is it likely to result in Yes spending or saving £250k or more, or to have a significant effect on two or more If yes give the reason why electoral wards? Project spend is over £250,000
Key Decision - Is it in the Council’s Yes Forward Plan (key decisions and private 14th September 2018 reports?)
The Decision - Is it eligible for call in by Yes Scrutiny?
Date signed off by Strategic Director & Karl Battersby – 5 November 2018 name
Is it also signed off by the Service Eamonn Croston – 26 October 2018 Director - Finance?
Is it also signed off by the Service Director - Legal Governance and Julie Muscroft - 26 October 2018 Commissioning? Cabinet member portfolio Cllr Cathy Scott Housing and Democracy
Electoral wards affected: All
Ward councillors consulted: Portfolio Lead, Cllr Cathy Scott
Public or private: Public
1.1The Council`s Decent Homes programme was delivered between 2003 and 2017, during this period we spent over £313m on council housing improvements. The principled approach was based on a criteria which determined where property components were failing and prioritised a programme of replacements. 1.2 Components were typically assessed in isolation from each other as the criteria stipulated 2 failed major components resulted in a Non-Decent Home (DCLG quality criteria). We therefore replaced the minimum amount of components to ensure compliance to the Decency Standard at any time.
1.3The installation date of a component triggered the next replacement date based on agreed lifecycles so we returned to properties occasionally to replace single components, in some cases visited the same home at intervals of 2, 3 or 4 years. We therefore delivered over 15 years of mainly single element schemes: window and door replacements, kitchen or bathroom, heating or rewire, roofing
1.4The proposed 5 year HRA Capital plan establishes a combined elemental approach and will support improvements in the way we deliver capital programmes and deploy our workforce; it will develop trade skills, promote multi-skilling, and will provide opportunity to recruit and train into property services helping to overcome anticipated shortages in skilled labour and an ageing workforce.
1.5The plan will deliver more property improvements resulting in a better quality homes for council tenants and reduce long term and duplicated disruption associated with return visits to replace single components. Once established we will supplement by delivering environmental improvements to the surrounding areas; we are currently trialling a pilot to 6 storey blocks at Newsome which include improvements to parking, lighting, paths and roads, amenity space, block appearance and communal facilities:
1.6The plan will deliver improvements in the way we provide key property services to our tenants, develop social value, reduce cost and improve the quality of existing social housing in Kirklees:
Reduced disruption to tenants by combining more components into one visit Combining Improvements to the environment; parking, lighting, roads, paths, green spaces Suitable/sustainable specifications/materials to meet modern day living and digital inclusion Use of local suppliers for goods and specialist services Apprenticeships, training and employment opportunities for Kirklees residents Reduced costs: prelim and delivery – average saving of between £4-5000.00 per property over the existing elemental approach (established during 8 pilot properties in 2017) Establishing housing stock at an acceptable baseline condition and aligning future programmes for cost certainty and financial planning Improve workforce planning and deployment, increased productivity and efficiency through multi-skilling
2.0Decision required
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HRA 5 Capital PlanReport | 15 pages | DownloadRead as text |
Follow Cabinet at Kirklees and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... | Noted | Open |
| 3 Nov 2026 | 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... | Approved | Open |
| 3 Nov 2026 | 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... | Approved | Open |
| 6 Oct 2026 | 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... | Noted | Open |
| 6 Oct 2026 | 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.