It was resolved that: (1) Eamonn Croston, Service Director for Finance, IT and Transactional Services be thanked for attending the meeting; (2) The costs associated with children excluded from school be brought to the next meeting of the Corporate Scrutiny Panel as part of the finance update; (3) The Panel recommend that schemes relating to the development of the high street be developed in readiness for the distribution of the pot of money being made available by Government for “changes to local high streets”.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
To receive information on financial monitoring for General Fund Revenue, Housing Revenue Account (HRA) and Capital Plan, as at Quarter 2 (month 6), 2018-19.
Key decision – is it likely to result in Yes spending or saving £250k or more, or to have a significant effect on two or more electoral wards? Key decision - is it in the Council’s Key decision - Yes Forward Plan (key decisions and private reports?
The Decision - Is it eligible for “call in” Yes by Scrutiny? Date signed off by Strategic Director & Rachel Spencer Henshall – name
Is it also signed off by the Service Eamonn Croston – Director for Finance ?
Is it also signed off by the Service Director – Legal, Governance & Julie Muscroft – Commissioning ?
Cabinet member portfolio - Corporate Give name of Portfolio Holders Cllr Graham Turner
1.1The Council’s General Fund controllable (net) revenue budget for 2018-19 was set at £291.2m. The budget includes planned (net) revenue savings of £16.2m in 2018-19.
1.2A further £3.7m ‘temporary resources’ has been added to this budget in-year, reflecting planned drawdown from “one-off” earmarked reserves to fund a number of “one-off” deferred expenditure commitments/other developments. This includes £1.6m from the revenue grants reserve, £1.5m from the revenue rollover reserve (previous year approvals) and £0.6m from the adverse weather reserve. There is also an assumed contribution to Financial Resilience Reserves of £4.1m, released out of Central budgets from the overprovision of MRP (Minimum Revenue Provision). See also paragraph 1.11. This results in a net transfer to reserves of £0.4m and a revised budget of £290.8m at Quarter 2.
1.3There is a forecast overspend of £4.8m against the £290.8m revised budget at Quarter 2; equivalent to 1.7 % variance against revised budget. This represents the following:
i) The council is making good progress with a forecast headline delivery of £12.6m against £16.2m planned savings; equivalent to 78%.forecast delivery. The balance of forecast undelivered savings of £3.6m includes continued pressures on schools transport at £1.6m and volume pressures on external residential placements plus other volume led placements within Children’s at £1.1m.
ii) There are £1.2m net unplanned pressures elsewhere including £7.9m relating to High Needs, offset by the release of £5m MRP saving and £400k from treasury management budgets within Central.
1.4The forecast revenue outturn as at Quarter 2 is summarised by Strategic Director Portfolios in Table 1 below.
Table 1 - Overview of 2018-19 general fund forecast revenue outturn position at Quarter 2
Annual forecast Strategic Revised Director Budget Forecast Variance Portfolios £000 £000 £000 Children & 75,610 83,936 8,326 Families Adults & Health 105,950 105,936 (14) Economy & 41,108 43,185 2,077 Infrastructure Corporate 29,455 29,215 (240) Services Central Budgets 38,707 33,310 (5,397) Grand Total 290,830 295,582 4,752
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.