Resolved

(1) That authority be given for the payment of a grant of £2m from the Council’s capital plan to contribute to the regeneration and bringing back into use of Pioneer House so as to bring about the completion of the Dewsbury Learning Quarter thereby increasing footfall and the regeneration of Dewsbury Town centre. (2) That authority be delegated to the Service Director (Legal, Governance and Monitoring) to enter in to all documentation necessary to bring about the ability for the Council to make a grant of £2m to Kirklees College from the Capital Plan.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet, 5 pages

Purpose of report

To seek authority to amend a previous Cabinet authority (from January 2017) with regard to the underwriting of WYCA loan costs to Kirklees College.

Key Decision - Is it likely to result in Yes spending or saving £250k or more, or to have a significant effect on two or more electoral The Chair of Overview and Scrutiny wards? Management Committee has agreed to the addition of an urgent item to the Forward Plan in relation to this issue. Key Decision - Is it in the Council’s Forward Yes Plan (key decisions and private reports?) The Decision - Is it eligible for call in by No. The Chair of Overview and Scrutiny Scrutiny? Management Committee has waived the right to call in due to the need for a decision to confirm the allocation of funding to the Pioneer House College fit out works to be confirmed to the college as soon as possible. Date signed off by Strategic Director & name Karl Battersby - 23.11.2018

Is it also signed off by the Service Director for Finance (S151 Officer)? Eamonn Croston - 22.11.2018

Is it also signed off by the Service Director for Legal Governance and Commissioning? Julie Muscroft - 21.11.2018

Cabinet member portfolio Cllr Graham Turner - Corporate

Electoral wards affected: Dewsbury East, Dewsbury West, Dewsbury South

Ward councillors consulted: Dewsbury East – Cllrs E Firth, C Scott and P Kane, Dewsbury South – Cllrs M Ahmed, G Asif and N Dad, Dewsbury West – Cllrs M Hussain, D O’Donovan, and M Pervaiz

Public or private: Public

GDE-GOV-REPORTTEMPLATE-v3-02/17 NEW 1. Summary

This report seeks to revise the authority previously given by Cabinet in January 2017 in relation to the underwriting of loan costs by the Council for Kirklees College for Pioneer House.

2. Information required to take a decision

Background

The Council acquired Pioneer House on 19 July 2011 following a Compulsory Purchase Order. The first priority for the Council was to protect the building from further deterioration by making it wind and water tight. This package of work cost £2.5m and was completed in September 2013.

Cabinet on 08th March 2016 endorsed the Council’s commitment to work with Kirklees College with a view to bringing Pioneer House back in to use as a new education facility. Cabinet on 15th November 2016 approved the disposal of land at Bradford Road, Dewsbury to Kirklees College to facilitate an early commencement of the Dewsbury Learning Village (now known as the Dewsbury Learning Quarter (DLQ)).

A subsequent Cabinet report on 17th January 2017 gave approval for the release of funding from the capital plan to fund a programme of landlords works, to grant a lease to Kirklees college, for the Council to underwrite Heritage Lottery Fund grant, and for the Council to underwrite 50% of the risk of repayment of the loan from West Yorkshire Combined Authority (WYCA). It is the issue of repayment of the loan which is the focus of this report.

2.2Current position

In terms of the overall construction programme, the landlord’s (Council’s) works are progressing well and are due for completion early in 2019. Following the completion of the landlord’s works, the college will undertake an internal fit-out programme of works, forming new classrooms, offices, and art and design workshops.

2.3Loan repayment

The issue which has arisen in relation to loan repayment relates to the authority given by Cabinet in January 2017. The wording of the report at that time was that the Council would “repay 50% of the loan up to a maximum of £2 million”. In developing their plans for the DLQ, the college had access to up to a maximum £2 million contribution to the overall loan funding from the Council. The £2 million remains in the Council’s capital plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pioneer House: Contribution to College Fit Out Works (Late/Urgent Item)Report 5 pages DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open