CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Kirklees Council
Cabinet, Tuesday 16 July 2019 at 4.00pm

7

Noted Executive 1 paper

Cabinet noted this item on Tuesday 16 July 2019. Below is the council's own wording, with the papers it was decided on.

Item7:

Resolved

1) That the additional capital grant being provided by the DfE for Special Provision projects, as detailed within paragraph 2.2 of the considered report, be noted. 2) That approval be given to the proposed capital allocations for projects at Ravenshall School, Newsome High School and Honley High School, as detailed in the considered report, which would be funded from the Learning and early Support Special Provision grant baseline section of the Capital Plan and that authorisation be given for the projects to be designed, procured and implemented within the overall programme budget of £1.794m. 3) That approval be given to capital allocations for modular projects at Brambles Primary Academy and Hanging Heaton CE (VC) Junior and Infant School, to be funded from the Learning and Early Support Basic Need Grant baseline section of the Capital Plan, enabling the specified projects to be implemented on site. 4) That approval be given to delegate powers, in accordance with Financial Procedure Rule 3.16, to the Service Director for Economy and Skills to manage the implementation of the works identified within the considered report within the respective agreed total programme budgets, including authority to transfer resources between schemes and within the overall programme budget to enable the successful delivery of the individual projects.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet

Purpose of report

This report will identify potential schools’ projects, for Member approval, to be funded from the 2019/20 to 2023/24 Learning and Early Support Special Provision grant and Basic Need baseline sections of the Capital Plan.

Key Decision - Is it likely to result in Yes – this will result in capital expenditure spending or saving £250k or more, or to significantly in excess of £250K have a significant effect on two or more electoral wards? Key Decision - Is it in the Council’s Yes Forward Plan (key decisions and private report?

The Decision - Is it eligible for “call in” by Yes Scrutiny?

Date signed off by Strategic Director & name Karl Battersby - 08/07/2019

Date signed off by the Service Director - Finance? Eamonn Croston - 05/07/2019

Date signed off by the Service Director - Legal, Governance and Commissioning? Julie Muscroft - 05/07/2019

Cabinet member portfolio Learning & Aspiration - Cllr Carol Pattison Corporate - Cllr Graham Turner

Electoral wards affected: Dewsbury East, Dewsbury South, Greenhead, Newsome, Holme Valley North

Ward councillors consulted: No

Public or private: Public

Has GDPR been considered? There are no GDPR implications arising from this report. 1. Summary

1.1This report will give an update on specific school based Special Educational Needs and Disability (SEND) capital projects, identified to be funded from the Learning & Early Support Special Provision government grant baseline section of the Council’s Capital Plan. This report, asks that Members approve the allocation of further top-up SEND funding, announced by the Department for Education (DfE) in May and December 2018.

1.2In addition, Members will be asked to approve the allocation of the capital required to fund new modular accommodation at Brambles Primary Academy and Hanging Heaton CE (VC) J&I Schools from the 2019/20 Learning & Early Support Basic Need baseline budget for New Pupil Places.

1.3Members will also be asked to delegate authority to officers to manage the delivery of the proposed works within the respective project and programme budget envelopes.

2. Information required to take a decision

(a) Special Provision Grant

2.1The DfE first announced the Special Provision fund on 4th March 2017 to support Local Authorities (LAs) to make capital investment in provision for pupils with SEND. £1.056m was allocated to Kirklees Council to be split equally over three years from 2018/19 to 2020/21 at a rate of £352k per annum.

2.2On 29th May 2018, the DfE announced a £50m top-up across all LAs resulting in an additional allocation of £246k to Kirklees. A further £100m top-up was announced in December 2018 with another £492k for Kirklees, bringing the total capital grant available for the Council to £1.794m

2.3As part of the conditions of the grant, all LAs were required by the DfE to carry out a high quality collaborative review of their high needs provision for children and young people in their local area with complex SEND by 31 March 2018. A detailed programme for expenditure of the grant was required as an output of the review.

2.4On 20 March 2018 Cabinet approved the allocation of the Special Provision grant available at that time to three specific schemes that had been identified by the High Needs Review as the most efficient way of using the capital. These were schemes at Ravenshall School, Honley High School and Newsome High School. After the initial feasibility studies were undertaken, it was found that the estimated costs exceeded the notional budget allocated by Cabinet. However, the additional funding allocated by the DfE obviated the need to consider reductions in the aspirations or objectives of the projects.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2019/20 to 2023/24 Council Capital Plan: Proposed allocation of capital funding from the Directorate for Children's Learning & Early Support baseline sections of the Capital PlanReport 162 KB DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies