Thursday 11th July 2019
Present: Councillor Steve Hall (Chair) Councillor Donald Firth Councillor Paul Kane Councillor Mohan Sokhal Councillor Carole Pattison Councillor Charlotte Goodwin Councillor Andrew Pinnock
1 Membership of the Committee There were no substitutions of membership.
2 Interests and Lobbying Councillor Kane advised that he would not participate in the consideration and determination of Agenda Item 12 (Application 2019/90616) on the grounds that he knew the applicant.
3 Admission of the Public It was noted that all agenda items would be considered in public session.
4 Deputations/Petitions None received.
5 Public Question Time None received.
6 Site Visit - Application No: 2019/90661 Site visit undertaken.
7 Site Visit - Pre Application Enquiry: 2018/20078 Site visit undertaken.
8 Site Visit - Application No: 2019/91491 Site visit undertaken.
9 Planning Application - Application No: 2019/91491 The Committee gave consideration to Application 2018/91491 – Demolition of existing fitness complex and erection of Spen Valley Leisure Centre at Spenborough Fitness Complex, Bradford Road, Littletown.
Under the provisions of Council Procedure Rule 37, the Committee received representations from Rob Plant and Phil Brock (on behalf of the applicant).
1 Strategic Planning Committee - 11 July 2019
RESOLVED -
(1) That authority be delegated to the Head of Development and Master Planning to approve the application, issue the decision notice and complete the list of conditions including matters relating to;
- development to commence within three years - development to be built in accordance with approved plans - samples of materials to be approved - areas to be drained and surfaced - travel plan to be submitted - method of storage/access for waste - construction access - removal of PD rights to prevent enclosure of footpath - noise restriction from fixed plant and equipment - submission of phase 2 report - submission of remediation strategy - implementation of remediation strategy - submission of validation report - details of travel plan implemented - electrical vehicle charging points - submission of aboricultural impact assessment - submission of aboricultural method statement - submission of drainage details and attenuation - submission of scheme for fats, oils and grease - temporary drainage, pollution prevention and flood risk (construction phase) - details of interceptors - details of floor warning and evacuation plan - details to protect public water supply - details of satisfactory outfall for surface water - submission of an ecological design strategy
(2) That authority be delegated to the Head of Strategic Investment to secure the signing of a Legal Agreement to provide a travel plan monitoring fee (£2k per annum).
(3) That, pursuant to (2) above, in circumstances where the Legal Agreement has not been completed within three months of this decision, the Head of Development and Master Planning shall be authorised to consider whether permission should be refused on the grounds that the proposals are unacceptable in the absence of the benefits that would have been secured, and would therefore be permitted to determine the Application and impose appropriate reasons for refusal under delegated powers.
A Recorded Vote was taken in accordance with Council Procedure Rule 42 (5) as follows;
For: Councillors D Firth, Goodwin, S Hall, Kane, Pattison, A Pinnock and Sokhal (7 votes) Against: (no votes)
2 Strategic Planning Committee - 11 July 2019
10 Planning Application - Application No: 2019/90890 The Committee gave consideration to Application 2019/90890 – Development of a synchronous gas-powered standby generation facility, plus ancillary infrastructure, equipment, and access at land off Bradford Road, Batley.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
04. Minutes 11.07.19Minutes | 6 pages | DownloadRead as text |
PDF |
Minutes of the Previous MeetingsMinutes | 11 pages | Download |
Follow Strategic Planning Committee at Kirklees and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Oct 2026 | Planning Application - Application No: Planning Application 2021/93621Application approved (delegated). | Approved | Open |
| 23 Jul 2026 | Planning Application - Application No: 2025/92713Application approved (delegated). | Approved | Open |
| 11 Jun 2026 | Minutes of the Previous MeetingRESOLVED – The Minutes of the meeting held on 2 April 2026 be considered at the next meeting for approval. | Approved | Open |
| 11 Jun 2026 | Planning Application - Application No: 2025/92713Deferred. | Deferred | Open |
| 11 Jun 2026 | Planning Application - Application No: 2023/91907Approval delegated. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.